7107-7109 N COLBATH AVE 91405

Certificate Information: 7107-7109 N COLBATH AVE 91405

Application / Permit
22016-20000-16174
Plan Check / Job No.
B22VN08250
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF 20'-0" x 18'-4" (E) ATTACHED GARAGE AND (E) 13'-0" x 11'-6" S.F.D. TO A (N) ADU TO COMPLY WITH GCS 65852.2(e)(1)(A) . ALL WORK PER WFPP
Permit Issued
Issued on 6/15/2022
Issuing Office
Current Status
CofO Issued on 5/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/27/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 ALFRED RAMIREZ
Corrections Issued 6/2/2022 ALFRED RAMIREZ
Issued 6/15/2022 APPLICANT
Building Plans Picked Up 6/16/2022 APPLICANT
CofO in Progress 5/26/2023 RYAN SALAZAR
Permit Finaled 5/26/2023 MICHAEL SMITH
CofO Issued 5/26/2023 MICHAEL SMITH
Permit Finaled 5/26/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/2/2022 ROMAN GUTIERREZ
Sewer availability Cleared 6/2/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 6/3/2022 ROMAN GUTIERREZ
Public Works-Highway Ded. Cleared 6/3/2022 ROMAN GUTIERREZ
Public Works-Open Permits Cleared 6/3/2022 ROMAN GUTIERREZ
Public Works-Sewers Cleared 6/3/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/23/2022 Approved JOHN COLEMAN
Footing/Foundation/Slab 11/23/2022 Approved JOHN COLEMAN
Underground Mechanical 11/23/2022 Approved JOHN COLEMAN
BUILDING-Rough-Frame 2/3/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 2/3/2023 Approved RYAN SALAZAR
Green Building Rough 2/3/2023 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 2/3/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/3/2023 Approved RYAN SALAZAR
PLUMBING-Rough 2/3/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 2/9/2023 Approved RYAN SALAZAR
Insulation 2/9/2023 Approved RYAN SALAZAR
Drywall Nailing 2/13/2023 Approved WILLIAM WREN
Green Building Rough 2/13/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 5/23/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 5/23/2023 Approved RYAN SALAZAR
Final 5/23/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 5/23/2023 Approved RYAN SALAZAR
HVAC-Final 5/23/2023 Approved RYAN SALAZAR
PLUMBING-Final 5/23/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 5/23/2023 Approved RYAN SALAZAR