21820 W MICHALE ST 91304

Certificate Information: 21820 W MICHALE ST 91304

Application / Permit
22016-20000-16170
Plan Check / Job No.
B22VN08246
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC: MAJOR INTERIOR AND EXTERIOR REMODEL, PER ENG.
Permit Issued
Issued on 6/10/2022
Issuing Office
Current Status
Permit Finaled on 11/16/2023

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 5/28/2022 YAQUB MIRZA
Plan Check Approved 5/28/2022 YAQUB MIRZA
Building Plans Picked Up 6/2/2022 APPLICANT
Issued 6/10/2022 APPLICANT
Permit Finaled 11/15/2023 CHRIS CHRISTENSEN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Supreme Remodeling Inc; Lic. No.: 939981-B 14545 VICTORY BLVD UNIT 401      VAN NUYS, CA 91411
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/27/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 6/27/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 6/29/2022 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/29/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 6/29/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/30/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/5/2022 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/14/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/14/2022 Approved CHRIS CHRISTENSEN
Insulation 7/19/2022 Partial Approval JESUS PINEDA
Shower Pan 7/19/2022 Approved JESUS PINEDA
Insulation 7/22/2022 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/22/2022 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 8/5/2022 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/8/2022 Partial Approval CHRIS CHRISTENSEN
Wood Frame 8/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/9/2022 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 8/9/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/17/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 8/17/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/29/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 8/29/2022 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 1/27/2023 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 1/27/2023 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Partial Approval CHRIS CHRISTENSEN
Final 9/14/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/14/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 9/14/2023 Approved CHRIS CHRISTENSEN
Final 11/15/2023 Permit Finaled CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Approved CHRIS CHRISTENSEN