4247 N GREENBUSH AVE 91423

Certificate Information: 4247 N GREENBUSH AVE 91423

Application / Permit
22016-20000-16116
Plan Check / Job No.
B22VN08209
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 2/27/2025
Issuing Office
West Los Angeles
Current Status
Issued on 2/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 SERGIO MUNIZ
Corrections Issued 5/26/2022 SERGIO MUNIZ
Building Plans Picked Up 6/1/2022 APPLICANT
Plan Check Approved 2/26/2025 MOHAMMAD ESMAILI
Issued 2/27/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/25/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/25/2023 CARLOS AGUILERA
Sewer availability Cleared 4/25/2023 CARLOS AGUILERA
Construction near power lines Cleared 2/18/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 5/9/2025 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 5/9/2025 Partial Approval ARAM AVEDISIAN
Sewer 5/9/2025 Approved ARAM AVEDISIAN
Underground Mechanical 5/14/2025 Partial Approval JOSE AVILA
PLUMBING-Rough 6/27/2025 Approved JAVIER RAMOS JR
Pre-Inspection 6/27/2025 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 7/11/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/14/2025 Corrections Issued MISAEL ESPARZA
Reinforced Concrete Frame 7/14/2025 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 9/16/2025 Approved MISAEL ESPARZA
Reinforced Concrete Frame 9/16/2025 Partial Inspection MISAEL ESPARZA
Wood Frame 9/16/2025 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 10/21/2025 Partial Inspection MISAEL ESPARZA
Pre-Inspection 10/21/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/21/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 11/21/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 11/21/2025 Not Ready for Inspection MISAEL ESPARZA
Grounding or Bonding 11/21/2025 Partial Inspection MISAEL ESPARZA
HVAC-Rough 11/21/2025 Corrections Issued MISAEL ESPARZA
Wood Frame 11/21/2025 Partial Inspection MISAEL ESPARZA
ELECTRICAL-Rough 11/26/2025 Approved MISAEL ESPARZA
HVAC-Rough 11/26/2025 Approved MISAEL ESPARZA
Pre-Inspection 12/9/2025 Partial Approval JACK KARGODORIAN
Insulation 12/22/2025 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 12/22/2025 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 2/9/2026 Approved MISAEL ESPARZA
Green Building Rough 2/9/2026 Approved MISAEL ESPARZA
Insulation 2/9/2026 Approved MISAEL ESPARZA
Interior/Exterior Lathing 2/9/2026 Partial Approval MISAEL ESPARZA
Wood Frame 2/9/2026 Approved MISAEL ESPARZA
Drywall Nailing 3/20/2026 Approved MISAEL ESPARZA
Shower Pan 3/20/2026 Approved MISAEL ESPARZA