6623 N NESTLE AVE 91335

Certificate Information: 6623 N NESTLE AVE 91335

Application / Permit
22016-20000-16037
Plan Check / Job No.
B22VN08153
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) GARAGE AND STORAGE CONVERT TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 9/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2022 APPLICANT
Assigned to Plan Check Engineer 6/22/2022 PINANK PATEL
Corrections Issued 6/22/2022 PINANK PATEL
Building Plans Picked Up 6/28/2022 APPLICANT
Issued 9/23/2022 APPLICANT
CofO in Progress 3/11/2024 JEFFREY BULL
Permit Finaled 4/2/2024 JOHN JANSON
CofO Issued 4/2/2024 JOHN JANSON
Permit Finaled 4/2/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/1/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/1/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 7/1/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 9/6/2022 RIDWAN HARDY
Construction within easement Cleared 9/6/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Richard C C; Lic. No.: S1371 19321 VANOWEN ST      RESEDA, CA 91335

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/24/2022 Approved JEFFREY BULL
PLUMBING-Rough 10/24/2022 Partial Approval JEFFREY BULL
BUILDING-Rough-Frame 11/18/2022 Not Ready for Inspection JEFFREY BULL
Green Building Rough 11/18/2022 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 11/30/2022 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 11/30/2022 Corrections Issued JON MCHUGH
Green Building Rough 11/30/2022 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 11/30/2022 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 12/14/2022 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 12/14/2022 Partial Approval DAVID SANDOVAL
Green Building Rough 12/14/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 12/14/2022 Corrections Issued DAVID SANDOVAL
Interior/Exterior Lathing 12/28/2022 Partial Approval JEFFREY BULL
Rough-Elec/Plmb/HVAC 12/28/2022 Approved JEFFREY BULL
Insulation 1/6/2023 Approved JEFFREY BULL
Shower Pan 1/6/2023 Approved JEFFREY BULL
Drywall Nailing 1/17/2023 Approved JEFFREY BULL
PLUMBING-Rough 1/30/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 3/15/2023 Approved JEFFREY BULL
ELECTRICAL-Final 3/15/2023 Approved JEFFREY BULL
Final 3/15/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 3/15/2023 Approved JEFFREY BULL
Green Building Rough 3/15/2023 Approved JEFFREY BULL
HVAC-Final 3/15/2023 Approved JEFFREY BULL
PLUMBING-Final 3/15/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 3/15/2023 SGSOV Approved JEFFREY BULL
Service/Power Release 3/15/2023 Approved JEFFREY BULL
Smoke Detectors 3/15/2023 Approved JEFFREY BULL