1134 N ISABEL ST 90065

Certificate Information: 1134 N ISABEL ST 90065

Application / Permit
22016-20000-16035
Plan Check / Job No.
B22VN08150
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO THE (E) SINGLE FAMILY DWELLING TO REPLACE TWO WINDOWS, ADD TWO CLOSETS AND A BATHROOM AT FIRST FLOOR. ENCLOSE (E)WINDOW AT FIRST AND SECOND FLOOR.
Permit Issued
Issued on 7/27/2022
Issuing Office
Valley
Current Status
Permit Finaled on 6/28/2023

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 SARKIS HARABEDIAN
Corrections Issued 5/28/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 7/2/2022 ALEC MOUSAKHANIAN
Plan Check Approved 7/24/2022 SARKIS HARABEDIAN
Building Plans Picked Up 7/26/2022 APPLICANT
Issued 7/27/2022 APPLICANT
Permit Finaled 6/27/2023 OSVALDO PARAMO

Permit Application Clearance Information

Supp. Use District POD/CDO/TDO Cleared 6/22/2022 NASHYA JENSEN

Contact Information

Contractor Nelson General Building Contractor; Lic. No.: 649194-B 4227 S WESTERN AVE      LOS ANGELES, CA 90062

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Elec/Plmb/HVAC 8/3/2022 Corrections Issued OSVALDO PARAMO
Wood Frame 8/3/2022 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 12/1/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 12/1/2022 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 12/1/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 12/1/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/6/2022 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 12/6/2022 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 12/14/2022 Approved OSVALDO PARAMO
HVAC-Rough 12/14/2022 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 12/19/2022 Approved OSVALDO PARAMO
Insulation 12/19/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/19/2022 Partial Approval OSVALDO PARAMO
Wood Frame 12/19/2022 Approved OSVALDO PARAMO
Final 5/18/2023 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/18/2023 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 5/18/2023 Approved OSVALDO PARAMO
Final 6/2/2023 Partial Approval OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/2/2023 SGSOV Approved OSVALDO PARAMO
Final 6/27/2023 Permit Finaled OSVALDO PARAMO