9660 W SOMBRA VALLEY DR 91040
Certificate Information: 9660 W SOMBRA VALLEY DR 91040
- Application / Permit
- 22016-20000-16032
- Plan Check / Job No.
- B22VN08147
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) S.F.D. TO KITCHEN, DINING, BATHROOM, LAUNDRY, ADD AND REMOVE WINDOWS AND DOORS, REMOVE BEARING WALLS, ADD PARTION WALLS, ADD LANDINGS. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/9/2022
Permit Application Status History
| Submitted | 5/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2022 | ALFRED RAMIREZ |
| Corrections Issued | 5/27/2022 | ALFRED RAMIREZ |
| Issued | 6/14/2022 | APPLICANT |
| Building Plans Picked Up | 6/16/2022 | APPLICANT |
| Permit Finaled | 12/8/2022 | DAVID ANDERSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/3/2022 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/9/2022 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/13/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 9/13/2022 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 9/29/2022 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/5/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/5/2022 | Approved | DAVID ANDERSON |
| Gas Test | 10/5/2022 | Approved | DAVID ANDERSON |
| Green Building Rough | 10/5/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 10/5/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/5/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/12/2022 | Approved | DAVID ANDERSON |
| Insulation | 10/17/2022 | Approved | DAVID ANDERSON |
| Drywall Nailing | 10/21/2022 | Approved | DAVID ANDERSON |
| Shower Pan | 10/21/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/24/2022 | Approved | DAVID ANDERSON |
| Final | 12/8/2022 | Permit Finaled | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 12/8/2022 | Approved | DAVID ANDERSON |