143 N HOBART BLVD 90004

Certificate Information: 143 N HOBART BLVD 90004

Application / Permit
22016-20000-16004
Plan Check / Job No.
B22VN08123
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NON-STRUCTURAL INTERIOR REMODEL TO RELOCATE/REMODEL KITCHEN. RELOCATE BEDROOM AND ADD NEW BATHROOM IN OTHER (E) BEDROOM. COMPLY WITH DEPARTMENT ORDER effective date 04/19/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 7/7/2022
Issuing Office
Current Status
Permit Finaled on 9/14/2022

Permit Application Status History

Submitted 5/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/31/2022 JEROME MAGAT PALMA
Plan Check Approved 5/31/2022 JEROME MAGAT PALMA
Building Plans Picked Up 5/31/2022 APPLICANT
Issued 7/7/2022 APPLICANT
Permit Finaled 9/14/2022 GLEN RAND

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

SGSOV-Seismic Gas S/O Valve 7/8/2022 SGSOV Not Ready GLEN RAND
Pre-Inspection 7/11/2022 Approved GLEN RAND
ELECTRICAL-Rough 8/17/2022 Corrections Issued GLEN RAND
PLUMBING-Final 8/17/2022 Corrections Issued GLEN RAND
PLUMBING-Rough 8/18/2022 Corrections Issued GLEN RAND
PLUMBING-Rough 8/19/2022 Approved GLEN RAND
ELECTRICAL-Final 8/22/2022 Approved GLEN RAND
ELECTRICAL-Rough 8/22/2022 Approved GLEN RAND
BUILDING-Rough-Frame 8/25/2022 Corrections Issued GLEN RAND
Footing/Foundation/Slab 8/25/2022 Corrections Issued GLEN RAND
BUILDING-Rough-Frame 8/26/2022 Partial Approval GLEN RAND
Interior/Exterior Lathing 8/26/2022 Approved GLEN RAND
PLUMBING-Final 8/26/2022 Corrections Issued GLEN RAND
BUILDING-Rough-Frame 9/12/2022 Approved GLEN RAND
Final 9/12/2022 Corrections Issued GLEN RAND
PLUMBING-Final 9/12/2022 Corrections Issued GLEN RAND
SGSOV-Seismic Gas S/O Valve 9/12/2022 SGSOV Approved GLEN RAND
Shower Pan 9/12/2022 Approved GLEN RAND
Smoke Detectors 9/12/2022 Approved GLEN RAND
Final 9/14/2022 Permit Finaled GLEN RAND