6926 N SHOUP AVE 91307
Certificate Information: 6926 N SHOUP AVE 91307
- Application / Permit
- 22016-20000-15923
- Plan Check / Job No.
- B22VN08071
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 451 SF DET GARAGE INTO A (N) 451 SF ADU PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Current Status
- CofO Issued on 9/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/26/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 6/9/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/10/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 6/14/2022 | APPLICANT |
| Issued | 6/21/2022 | APPLICANT |
| CofO in Progress | 8/4/2022 | TROY SANDERS |
| Permit Finaled | 9/10/2022 | DANIEL ORRANTE |
| CofO Issued | 9/10/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/10/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/1/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/1/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/1/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/1/2022 | MEGAN GODINEZ |
Contact Information
| Architect | Carter,, Robert Alan; Lic. No.: C12833 | 21121 E LARIAT COURT WALNUT, CA 91789 |
| Contractor | Bohler Builders Group Inc; Lic. No.: 957685-B | 615 WILLOW SPRINGS LANE GLENDORA, CA 91741 |
| Engineer | Freitas,, Richard Gomes; Lic. No.: C49072 | 240 COPA DE ORO DR BREA, CA 92823 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/23/2022 | Partial Approval | TROY SANDERS |
| Sewer | 6/23/2022 | Approved | TROY SANDERS |
| Underground Mechanical | 6/23/2022 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 6/24/2022 | Approved | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 6/27/2022 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 7/1/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 7/1/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 7/1/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 7/1/2022 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 7/5/2022 | Partial Approval | TROY SANDERS |
| Insulation | 7/7/2022 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2022 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 7/13/2022 | Approved | TROY SANDERS |
| Green Building Rough | 7/13/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 7/13/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 8/3/2022 | Approved | TROY SANDERS |
| Final | 8/3/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/3/2022 | Approved | TROY SANDERS |
| HVAC-Final | 8/3/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 8/3/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/3/2022 | Approved | TROY SANDERS |
| Verify Rec and Parks Fee Memo | 8/4/2022 | Approved | TROY SANDERS |