2923 W SUNSET BLVD 90026
Certificate Information: 2923 W SUNSET BLVD 90026
- Application / Permit
- 22016-20000-15909
- Plan Check / Job No.
- B22VN08061
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Beauty Shop or Parlor
- Work Description
- CHANGE OF USE FROM (E) RETAIL TO BEAUTY SALON
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Current Status
- CofO Issued on 3/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | RAPHAEL ROSAS |
| Corrections Issued | 5/25/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/7/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 7/1/2022 | RAPHAEL ROSAS |
| Issued | 8/2/2022 | APPLICANT |
| Building Plans Picked Up | 8/11/2022 | APPLICANT |
| CofO in Progress | 3/13/2023 | KATY RAMIREZ |
| Permit Finaled | 3/13/2023 | ERNESTO CORRAL |
| CofO Issued | 3/13/2023 | ERNESTO CORRAL |
| Permit Finaled | 3/13/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/31/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 5/31/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 5/31/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 5/31/2022 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 6/2/2022 | TREVOR QUAN |
Contact Information
| Contractor | Aurea Construction Inc; Lic. No.: 1012091-B | 100 RANCHO RD #7 PO BOX 282 THOUSAND OAKS, CA 91360 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 9/7/2022 | Partial Inspection | JONATHAN QUACH |
| Drywall Nailing | 9/19/2022 | Partial Inspection | JONATHAN QUACH |
| Drywall Nailing | 10/18/2022 | Approved | MARK FERRARI |
| T-Bar Ceiling | 10/18/2022 | Not Ready for Inspection | MARK FERRARI |
| Final | 11/28/2022 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 11/28/2022 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 11/28/2022 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 12/29/2022 | Partial Inspection | RONALD JIMENEZ |
| Smoke Detectors | 12/29/2022 | Approved | TIMOTHY POWELL |
| Wood Frame | 12/29/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 12/30/2022 | Corrections Issued | TIMOTHY POWELL |
| Final | 1/13/2023 | Partial Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Not Ready | KATY RAMIREZ |
| Final | 3/14/2023 | OK to Issue CofO | KATY RAMIREZ |