2923 W SUNSET BLVD 90026

Certificate Information: 2923 W SUNSET BLVD 90026

Application / Permit
22016-20000-15909
Plan Check / Job No.
B22VN08061
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Beauty Shop or Parlor
Work Description
CHANGE OF USE FROM (E) RETAIL TO BEAUTY SALON
Permit Issued
Issued on 8/2/2022
Issuing Office
Current Status
CofO Issued on 3/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2022 APPLICANT
Assigned to Plan Check Engineer 5/25/2022 RAPHAEL ROSAS
Corrections Issued 5/25/2022 RAPHAEL ROSAS
Applicant returned to address corrections 6/7/2022 RAPHAEL ROSAS
Plan Check Approved 7/1/2022 RAPHAEL ROSAS
Issued 8/2/2022 APPLICANT
Building Plans Picked Up 8/11/2022 APPLICANT
CofO in Progress 3/13/2023 KATY RAMIREZ
Permit Finaled 3/13/2023 ERNESTO CORRAL
CofO Issued 3/13/2023 ERNESTO CORRAL
Permit Finaled 3/13/2023 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 5/31/2022 MIGUEL GAMBOA
ZA Case Cleared 5/31/2022 MIGUEL GAMBOA
ZA Case Cleared 5/31/2022 MIGUEL GAMBOA
ZA Case Cleared 5/31/2022 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 6/2/2022 TREVOR QUAN
Sewer availability Cleared 6/2/2022 TREVOR QUAN

Contact Information

Contractor Aurea Construction Inc; Lic. No.: 1012091-B 100 RANCHO RD #7 PO BOX 282      THOUSAND OAKS, CA 91360

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 9/7/2022 Partial Inspection JONATHAN QUACH
Drywall Nailing 9/19/2022 Partial Inspection JONATHAN QUACH
Drywall Nailing 10/18/2022 Approved MARK FERRARI
T-Bar Ceiling 10/18/2022 Not Ready for Inspection MARK FERRARI
Final 11/28/2022 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 11/28/2022 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 11/28/2022 Not Ready for Inspection ALFREDO LOPEZ
Final 12/29/2022 Partial Inspection RONALD JIMENEZ
Smoke Detectors 12/29/2022 Approved TIMOTHY POWELL
Wood Frame 12/29/2022 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 12/30/2022 Corrections Issued TIMOTHY POWELL
Final 1/13/2023 Partial Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Not Ready KATY RAMIREZ
Final 3/14/2023 OK to Issue CofO KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV No Gas KATY RAMIREZ