6515-6517 N COMANCHE AVE 91306

Certificate Information: 6515-6517 N COMANCHE AVE 91306

Application / Permit
22016-20000-15880
Plan Check / Job No.
B22VN07996
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan convert existing attached garage to accessory dwelling unit per State Law and GCS 65852.2(e)(1)(A) ALL WORK DONE PER WFPP
Permit Issued
Issued on 6/23/2022
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 5/27/2022 ZAW HAN
Corrections Issued 6/1/2022 ZAW HAN
Plan Check Approved 6/21/2022 KHUONG TRUONG
Issued 6/23/2022 APPLICANT
CofO in Progress 5/26/2023 ALEXANDER HANDY
Permit Finaled 3/6/2024 JOHN JANSON
CofO Issued 3/6/2024 JOHN JANSON
Permit Finaled 3/6/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/15/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/15/2022 MEGAN GODINEZ
Sewer availability Cleared 6/15/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/16/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/16/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/16/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/16/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/28/2022 Conditional Approval STEVEN BACK
Footing/Foundation/Slab 7/8/2022 Approved STEVEN BACK
Sewer 8/12/2022 Not Ready for Inspection STEVEN BACK
Sewer 8/18/2022 Approved STEVEN BACK
Pre-Inspection 8/24/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 9/29/2022 Approved STEVEN BACK
PLUMBING-Rough 9/29/2022 Partial Approval STEVEN BACK
Pre-Inspection 9/29/2022 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 10/3/2022 No Access for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 10/19/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 10/19/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 11/21/2022 Not Ready for Inspection STEVEN BACK
Special/Order Compliance 11/21/2022 Partial Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 12/12/2022 Approved ALEXANDER HANDY
Drywall Nailing 12/12/2022 Approved ALEXANDER HANDY
Final 2/28/2023 Corrections Issued ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 2/28/2023 Approved ALEXANDER HANDY
Final 3/16/2023 Corrections Issued HENRY KIM
PLUMBING-Final 3/16/2023 Corrections Issued HENRY KIM
ELECTRICAL-Final 5/24/2023 Approved ALEXANDER HANDY
Final 5/24/2023 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 5/24/2023 Approved ALEXANDER HANDY
PLUMBING-Final 5/24/2023 Approved ALEXANDER HANDY