6515-6517 N COMANCHE AVE 91306
Certificate Information: 6515-6517 N COMANCHE AVE 91306
- Application / Permit
- 22016-20000-15880
- Plan Check / Job No.
- B22VN07996
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan convert existing attached garage to accessory dwelling unit per State Law and GCS 65852.2(e)(1)(A) ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2022 | ZAW HAN |
| Corrections Issued | 6/1/2022 | ZAW HAN |
| Plan Check Approved | 6/21/2022 | KHUONG TRUONG |
| Issued | 6/23/2022 | APPLICANT |
| CofO in Progress | 5/26/2023 | ALEXANDER HANDY |
| Permit Finaled | 3/6/2024 | JOHN JANSON |
| CofO Issued | 3/6/2024 | JOHN JANSON |
| Permit Finaled | 3/6/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 6/15/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/15/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/16/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/16/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/16/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/28/2022 | Conditional Approval | STEVEN BACK |
| Footing/Foundation/Slab | 7/8/2022 | Approved | STEVEN BACK |
| Sewer | 8/12/2022 | Not Ready for Inspection | STEVEN BACK |
| Sewer | 8/18/2022 | Approved | STEVEN BACK |
| Pre-Inspection | 8/24/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 9/29/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 9/29/2022 | Partial Approval | STEVEN BACK |
| Pre-Inspection | 9/29/2022 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 10/3/2022 | No Access for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 10/19/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 10/19/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 11/21/2022 | Not Ready for Inspection | STEVEN BACK |
| Special/Order Compliance | 11/21/2022 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/12/2022 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 12/12/2022 | Approved | ALEXANDER HANDY |
| Final | 2/28/2023 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 2/28/2023 | Approved | ALEXANDER HANDY |
| Final | 3/16/2023 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 3/16/2023 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 5/24/2023 | Approved | ALEXANDER HANDY |
| Final | 5/24/2023 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 5/24/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 5/24/2023 | Approved | ALEXANDER HANDY |