6716 N JUMILLA AVE 91306
Certificate Information: 6716 N JUMILLA AVE 91306
- Application / Permit
- 22016-20000-15578
- Plan Check / Job No.
- B22VN07889
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED 19'-10" x 18'-0" TWO CAR GARAGE INTO A (N) ADU PER ENGINEERING. TO COMPLY WITH GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/13/2022
- Issuing Office
- Current Status
- CofO Issued on 2/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2022 | ALFRED RAMIREZ |
| Corrections Issued | 5/25/2022 | ALFRED RAMIREZ |
| Issued | 7/13/2022 | APPLICANT |
| Building Plans Picked Up | 7/15/2022 | APPLICANT |
| CofO in Progress | 2/23/2023 | ALEXANDER HANDY |
| Permit Finaled | 2/24/2023 | JOHN JANSON |
| CofO Issued | 2/24/2023 | JOHN JANSON |
| Permit Finaled | 2/24/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 6/8/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Xiaoran; Lic. No.: C78408 | 5233 AGNES AVE APT 107 VALLEY VILLAGE, CA 91607 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/1/2022 | Conditional Approval | STEVEN BACK |
| Pre-Inspection | 9/2/2022 | Approved | DAVID SCANTLIN |
| Sewer | 9/2/2022 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 9/9/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/20/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 9/20/2022 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 9/20/2022 | Not Ready for Inspection | STEVEN BACK |
| Sewer | 9/20/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/29/2022 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 9/29/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 9/29/2022 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 9/29/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/7/2022 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/7/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/7/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 10/7/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/19/2022 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 10/19/2022 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 10/27/2022 | Approved | STEVEN BACK |
| Green Building Rough | 10/27/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 10/27/2022 | Approved | STEVEN BACK |
| Insulation | 10/27/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/27/2022 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 11/7/2022 | No Access for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | No Access for Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 11/15/2022 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Approved | JEFFREY BULL |
| Drywall Nailing | 11/22/2022 | Approved | MORRIS JACKSON |
| Final | 12/21/2022 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 12/21/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 12/21/2022 | Approved | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 12/22/2022 | Conditional Approval | ALEXANDER HANDY |
| Final | 12/30/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 12/30/2022 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Not Ready | ALEXANDER HANDY |
| Final | 1/24/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 2/22/2023 | Approved | ALEXANDER HANDY |
| Final | 2/22/2023 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 2/22/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 2/22/2023 | Approved | ALEXANDER HANDY |