24260-24262 W HIGHLANDER ROAD 91307

Certificate Information: 24260-24262 W HIGHLANDER ROAD 91307

Application / Permit
22016-20000-15557
Plan Check / Job No.
B22VN07872
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: CONVERT EXISTING 2 CAR ATTACHED GARAGE TO JADU (453 SQ. FT) PER CA GOV'T CODE 65852.2(e)(1)(A) and 65852.22 PLUS 304 SQ. FT ADDITION TO SINGLE FAMILY HOUSE AND REMODELING
Permit Issued
Issued on 6/25/2022
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2022 APPLICANT
Assigned to Plan Check Engineer 5/23/2022 HANS SANTIAGO
Corrections Issued 5/24/2022 HANS SANTIAGO
Plan Check Approved 6/25/2022 ANDREW SANTIAGO
Issued 6/25/2022 APPLICANT
Re-Activate Permit 12/14/2022 KRISTEN BEVERIDGE
Permit Expired-Status Void 12/14/2022 KRISTEN BEVERIDGE
CofO in Progress 12/20/2022 KRISTEN BEVERIDGE
Permit Finaled 2/16/2023 DANIEL ORRANTE
CofO Issued 2/16/2023 DANIEL ORRANTE
Permit Finaled 2/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/26/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 5/26/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/31/2022 MEGAN GODINEZ
Sewer availability Cleared 5/31/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 5/31/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 5/31/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 5/31/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/30/2022 No Access for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/30/2022 No Access for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 6/30/2022 No Access for Inspection CHRIS CHRISTENSEN
Sewer 6/30/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Pre-Inspection 7/6/2022 Approved CHRIS CHRISTENSEN
Underground Mechanical 7/6/2022 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 7/7/2022 Conditional Approval KRISTEN CAUSEY
Footing/Foundation/Slab 7/11/2022 Approved CHRIS CHRISTENSEN
Underground Mechanical 7/11/2022 Approved CHRIS CHRISTENSEN
Underground Mechanical 7/26/2022 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/17/2022 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 8/17/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 8/17/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/13/2022 Conditional Approval CHRIS CHRISTENSEN
Drywall Nailing 9/13/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/13/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 9/13/2022 Approved CHRIS CHRISTENSEN
Insulation 9/13/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 9/13/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 9/23/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 9/23/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 11/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 11/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 11/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 11/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Final 11/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 11/8/2022 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/22/2022 Approved CHRIS CHRISTENSEN
Final 11/22/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 11/22/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 11/22/2022 Approved CHRIS CHRISTENSEN
Final 12/5/2022 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 12/5/2022 Not Ready for Inspection KRISTEN CAUSEY
Final 12/13/2022 Permit Expired-Status Void KRISTEN CAUSEY
Green Building Final 12/13/2022 Approved KRISTEN CAUSEY
HVAC-Final 12/13/2022 Approved KRISTEN CAUSEY
PLUMBING-Final 12/13/2022 Approved KRISTEN CAUSEY
Service/Power Release 12/13/2022 Approved KRISTEN CAUSEY
ELECTRICAL-Final 12/20/2022 Approved KRISTEN CAUSEY
Final 12/20/2022 OK to Issue CofO KRISTEN CAUSEY