13726 W RAYEN ST 91331

Certificate Information: 13726 W RAYEN ST 91331

Application / Permit
22016-20000-15551
Plan Check / Job No.
B22VN07867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
addition and convert (E) detached garage to ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 9/28/2022
Issuing Office
Current Status
CofO Issued on 1/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2022 APPLICANT
Assigned to Plan Check Engineer 5/23/2022 LUKE GONZALES
Corrections Issued 5/24/2022 LUKE GONZALES
Plan Check Approved 9/23/2022 SHANGQIN XIE
Issued 9/28/2022 APPLICANT
CofO in Progress 1/22/2024 GREGG CUMMINGS
Permit Finaled 1/24/2024 RUBEN SALAS
CofO Issued 1/24/2024 RUBEN SALAS
Permit Finaled 1/24/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 7/19/2022 RIDWAN HARDY
Address approval Cleared 9/19/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 9/19/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/21/2022 MEGAN GODINEZ
Sewer availability Cleared 9/21/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 9/21/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 9/21/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 9/21/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/17/2023 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 4/25/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 4/25/2023 Approved GREGG CUMMINGS
PLUMBING-Rough 4/25/2023 Approved GREGG CUMMINGS
ELECTRICAL-Rough 10/2/2023 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Partial Approval GREGG CUMMINGS
Green Building Rough 10/2/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 10/2/2023 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 10/17/2023 Partial Approval GREGG CUMMINGS
Green Building Rough 10/17/2023 Approved GREGG CUMMINGS
HVAC-Rough 10/17/2023 Approved GREGG CUMMINGS
PLUMBING-Rough 10/17/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 10/25/2023 Approved GREGG CUMMINGS
Insulation 10/25/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 10/25/2023 Partial Approval GREGG CUMMINGS
Drywall Nailing 11/6/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 11/6/2023 Approved GREGG CUMMINGS
Sewer 11/6/2023 Approved GREGG CUMMINGS
Underground Mechanical 11/6/2023 Partial Approval GREGG CUMMINGS
Final 12/20/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 12/20/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 12/20/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 12/27/2023 Approved GREGG CUMMINGS
Final 12/27/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 12/27/2023 Approved GREGG CUMMINGS
PLUMBING-Final 12/27/2023 Approved GREGG CUMMINGS
Service/Power Release 12/27/2023 Approved GREGG CUMMINGS