8102 W WILLOUGHBY AVE 90046
Certificate Information: 8102 W WILLOUGHBY AVE 90046
- Application / Permit
- 22016-20000-15411
- Plan Check / Job No.
- B22VN07806
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- UPGRADE AND REMODEL THE (E) KITCHEN, OPEN ONE WALL, ADD A NEW BEAM AND ADD A FRONT PATIO WITH OPEN TRELLIS.
- Permit Issued
- Issued on 6/27/2022
- Issuing Office
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | JESSE ARELLANO |
| Corrections Issued | 6/15/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/16/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/24/2022 | JESSE ARELLANO |
| Issued | 6/27/2022 | APPLICANT |
| Building Plans Picked Up | 7/14/2022 | APPLICANT |
| CofO in Progress | 2/10/2025 | JOSE MACIAS |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
| CofO Issued | 2/13/2025 | DEROLD HAUFF |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/7/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2022 | CHRISTOPHER ROCHA |
| Green Code | Cleared | 6/16/2022 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/31/2022 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 1/9/2023 | Corrections Issued | JULIAN AMAYA |
| PLUMBING-Rough | 1/9/2023 | Approved | JULIAN AMAYA |
| ELECTRICAL-Rough | 2/9/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 2/9/2023 | Partial Approval | MICHAEL LEWIS |
| Insulation | 2/9/2023 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 2/15/2023 | Approved | MICHAEL LEWIS |
| Insulation | 2/15/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 2/15/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 2/24/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 7/10/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 7/10/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 7/10/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 7/10/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 7/10/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 7/18/2023 | Approved | LILIANA PORTILLO |
| Final | 7/18/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 7/18/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 7/18/2023 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 7/18/2023 | Approved | LILIANA PORTILLO |
| Final | 2/10/2025 | OK to Issue CofO | JOSE MACIAS |