7950 N WOODLEY AVE 91406

Certificate Information: 7950 N WOODLEY AVE 91406

Application / Permit
22016-20000-15242
Plan Check / Job No.
B22VN07709
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Manufacturing
Work Description
T. I. TO TO CREATE A NEW SHOWROOM (NO RETAIL) WITHIN (E) WAREHOUSE AREA, REMODEL AN (E) RESTROOM, REMOVE 2 RESTROOMS AND ADD 3 NEW RESTROOMS, REPLACE 2 STALLS W/ NEW ADA STALLS, AND REPLACE (E) ROOFING MATERIALS
Permit Issued
Issued on 8/17/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 SEAN SHAHMIRI
Corrections Issued 5/31/2022 SEAN SHAHMIRI
Quality Review Completed 6/1/2022 OMID HEDAYAT
Building Plans Picked Up 6/1/2022 APPLICANT
Disabled Access Plans Picked Up 6/2/2022 APPLICANT
Plan Check Approved 8/8/2022 SEAN SHAHMIRI
Issued 8/17/2022 APPLICANT
CofO in Progress 3/29/2023 DEANDRE HOFFMAN
Permit Finaled 4/18/2023 JEFFREY DURAN
CofO Issued 4/18/2023 JEFFREY DURAN
Permit Finaled 4/18/2023 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/18/2022 LEE GUILBEAUX
Sewer availability Cleared 7/18/2022 LEE GUILBEAUX
ZA Case Cleared 7/19/2022 MIGUEL GAMBOA
DAS Clearance Cleared 7/27/2022 SEAN SHAHMIRI

Contact Information

Contractor Grijalva William General Contracting Inc; Lic. No.: 712934-B 32257 AGUA DULCE CANYON RD      SANTA CLARITA, CA 91390
Engineer Hoerner,, John Brent; Lic. No.: S2145 24024 VIA CANDELA      VALENCIA, CA 91355

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/13/2022 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 10/13/2022 Partial Inspection JEFFREY FULTON
Wood Frame 10/13/2022 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 10/17/2022 Partial Inspection JEFFREY FULTON
Wood Frame 10/17/2022 Partial Inspection JEFFREY FULTON
Wood Frame 10/18/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/20/2022 Partial Inspection JEFFREY FULTON
Wood Frame 10/27/2022 Partial Approval JONATHAN QUACH
Drywall Nailing 11/2/2022 Approved JEFFREY FULTON
Final 3/8/2023 Not Ready for Inspection DEANDRE HOFFMAN
Reinforced Masonry Frame 3/8/2023 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 3/8/2023 Approved DEANDRE HOFFMAN
Final 3/10/2023 Conditional Approval DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Approved DEANDRE HOFFMAN
Final 3/28/2023 OK to Issue CofO DEANDRE HOFFMAN