6245 N CARPENTER AVE 91606

Certificate Information: 6245 N CARPENTER AVE 91606

Application / Permit
22016-20000-15114
Plan Check / Job No.
B22VN07659
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTION OF 20' X 19' (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A), PER WFPP & ENGINEER CALCUATION.
Permit Issued
Issued on 6/1/2022
Issuing Office
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 5/20/2022 ALEC MOUSAKHANIAN
Corrections Issued 5/20/2022 ALEC MOUSAKHANIAN
Plan Check Approved 6/1/2022 ALEC MOUSAKHANIAN
Issued 6/1/2022 APPLICANT
Building Plans Picked Up 6/1/2022 APPLICANT
CofO in Progress 9/9/2022 JOHN HAYES
CofO Issued 9/10/2022 MICHAEL SMITH
Permit Finaled 9/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/20/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/20/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 5/20/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/20/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Neo Builders Inc; Lic. No.: 1061134-B 6238 ALCOVE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/21/2022 Conditional Approval JOHN HAYES
Footing/Foundation/Slab 6/22/2022 Not Ready for Inspection JOHN HAYES
Underground Mechanical 6/22/2022 Partial Approval JOHN HAYES
Footing/Foundation/Slab 6/29/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 7/7/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 7/7/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 7/7/2022 Not Ready for Inspection JOHN HAYES
HVAC-Rough 7/7/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 7/7/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/14/2022 Approved JOHN HAYES
Green Building Rough 7/14/2022 Approved JOHN HAYES
HVAC-Rough 7/14/2022 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 7/14/2022 Approved JOHN HAYES
Insulation 7/19/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 7/19/2022 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 7/22/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 7/22/2022 Approved JOHN HAYES
Green Building Rough 7/22/2022 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 7/22/2022 Approved JOHN HAYES
Drywall Nailing 7/26/2022 Approved JOHN HAYES
Interior/Exterior Lathing 7/26/2022 Approved JOHN HAYES
ELECTRICAL-Final 8/29/2022 Not Ready for Inspection JOHN HAYES
Final 8/29/2022 Corrections Issued JOHN HAYES
Green Building Final 8/29/2022 Not Ready for Inspection JOHN HAYES
HVAC-Final 8/29/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 8/29/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/29/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 8/29/2022 Not Ready for Inspection JOHN HAYES
Final 9/8/2022 OK to Issue CofO JOHN HAYES
Green Building Final 9/8/2022 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/8/2022 SGSOV Approved JOHN HAYES
Smoke Detectors 9/8/2022 Approved JOHN HAYES