12533 W KILLION ST 91607

Certificate Information: 12533 W KILLION ST 91607

Application / Permit
22016-20000-14505
Plan Check / Job No.
B22VN07371
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ALTERATIONS TO RECONFIGURE THE FLOOR PLAN TO CREATE TWO (N) BEDROOM AND A BATHROOM AND RELOCATE THE (E) KITCHEN - ALL WORK PER ENGINEER
Permit Issued
Issued on 11/7/2023
Issuing Office
Valley
Current Status
Permit Finaled on 3/22/2025

Permit Application Status History

Submitted 6/2/2022 APPLICANT
Assigned to Plan Check Engineer 6/3/2022 DANIEL ABRAMYAN
Corrections Issued 6/4/2022 DANIEL ABRAMYAN
Plan Check Approved 7/7/2022 DANIEL ABRAMYAN
Building Plans Picked Up 7/8/2022 APPLICANT
Issued 11/7/2023 APPLICANT
Permit Finaled 3/21/2025 OGANES TARAKHCHYAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/23/2022 MEGAN GODINEZ
Sewer availability Cleared 6/23/2022 MEGAN GODINEZ
Specific Plan Cleared 6/23/2022 ERIN NASH
ZI Cleared 6/23/2022 ERIN NASH
ZI Cleared 6/23/2022 ERIN NASH
Public Works-Highway Ded. Cleared 6/23/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/23/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/23/2022 MEGAN GODINEZ

Contact Information

Contractor Seashell Builders Group Inc; Lic. No.: 1097249-B 5300 CALHOUN AVENUE      SHERMAN OAKS, CA 91401
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/14/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 12/20/2023 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 12/21/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 12/26/2023 Partial Approval JOSE AVILA
Footing/Foundation/Slab 12/28/2023 Partial Approval JOSE AVILA
ELECTRICAL-Rough 1/17/2024 Partial Approval JOSE AVILA
HVAC-Rough 1/17/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 1/17/2024 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 1/18/2024 Partial Approval JOSE AVILA
Deputy Wood Construction 1/18/2024 Conditional Approval ROBERT GOLD
Insulation 1/18/2024 Partial Approval JOSE AVILA
Interior/Exterior Lathing 1/18/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Partial Inspection ROBERT GOLD
Drywall Nailing 1/23/2024 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 4/2/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 4/4/2024 Approved JOSE AVILA
PLUMBING-Rough 4/4/2024 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 4/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/8/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/9/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 4/9/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/11/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 7/11/2024 Approved OGANES TARAKHCHYAN
Insulation 7/15/2024 Approved DAVID ANDERSON
Deputy Wood Construction 7/17/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/18/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/29/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 3/21/2025 Approved OGANES TARAKHCHYAN
Final 3/21/2025 Permit Finaled OGANES TARAKHCHYAN
PLUMBING-Final 3/21/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 3/21/2025 Approved OGANES TARAKHCHYAN