901 N VINE ST 90038

Certificate Information: 901 N VINE ST 90038

Application / Permit
22016-20000-14241
Plan Check / Job No.
B22VN07222
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT (E) 21'-1.5" X 36'-8", 18'-10" X 36'-8" & 30'-3" X 36'-8" IRREGULAR SHAPED PORTION OF GARAGE AT 1ST FLOOR TO (3) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(C). ALL WORK PER ENGINEERING. SEE COMMENTS.
Permit Issued
Issued on 1/6/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 RAPHAEL ROSAS
Disabled Access Plans Picked Up 6/3/2022 APPLICANT
Corrections Issued 6/6/2022 RAPHAEL ROSAS
Quality Review Completed 6/13/2022 STEVEN KIM
Building Plans Picked Up 6/13/2022 APPLICANT
Green Plans Picked Up 6/13/2022 APPLICANT
Applicant returned to address corrections 11/17/2022 RAPHAEL ROSAS
Plan Check Approved 12/7/2022 RAPHAEL ROSAS
Issued 1/6/2023 APPLICANT
CofO in Progress 8/7/2024 TIMOTHY POWELL
CofO Issued 8/8/2024 RAFAEL ESPINOZA
Permit Finaled 8/8/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 7/7/2022 JEANIE LAM
Sewer availability Cleared 7/7/2022 JEANIE LAM
"D" conditions Cleared 7/20/2022 ANACANY HURTADO
ZA Case Cleared 7/20/2022 ANACANY HURTADO
ZI Cleared 7/20/2022 ANACANY HURTADO
Miscellaneous Cleared 7/22/2022 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 8/15/2022 JEANIE LAM
DAS Clearance Cleared 10/17/2022 OLLIE CARTER
Fire Marshal Fire Life Safety Cleared 11/28/2022 RONILO MULAWIN
Green Code Cleared 11/29/2022 MICHAEL AYERS

Contact Information

Contractor Hy-Max Building Corp; Lic. No.: 702339-B 425 W BROADWAY #410      GLENDALE, CA 91204
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Masonry 1/18/2023 Conditional Approval MICHAEL ROSENBERG
Pre-Inspection 2/3/2023 Approved RONALD JIMENEZ
Reinforced Masonry Frame 2/3/2023 Partial Approval RONALD JIMENEZ
Masonry Wall/Backfill 2/23/2023 Partial Approval VAHE KELEDJIAN
Reinforced Masonry Frame 2/23/2023 Partial Approval VAHE KELEDJIAN
Masonry Wall/Backfill 3/9/2023 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 7/27/2023 Not Ready for Inspection VAHE KELEDJIAN
Footing/Foundation/Slab 8/8/2023 Not Ready for Inspection RONALD JIMENEZ
Special/Order Compliance 9/12/2023 Approved RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Conditional Approval VAHE KELEDJIAN
Light Gage Steel Frame 10/11/2023 Not Ready for Inspection RONALD JIMENEZ
Special/Order Compliance 10/25/2023 Approved RONALD JIMENEZ
Pre-Inspection 1/17/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 2/22/2024 Approved JEROME BLACKWOOD
Insulation 2/27/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 3/1/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 3/6/2024 Partial Approval TIMOTHY POWELL
Insulation 3/8/2024 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 3/11/2024 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 3/13/2024 Partial Approval TIMOTHY POWELL
Drywall Nailing 3/19/2024 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 4/12/2024 Partial Approval TIMOTHY POWELL
Drywall Nailing 4/18/2024 Approved TIMOTHY POWELL
Pre-Inspection 6/21/2024 Approved TIMOTHY POWELL
Final 7/2/2024 Not Ready for Inspection TIMOTHY POWELL
Green Building Final 7/2/2024 Approved TIMOTHY POWELL
Green Building Rough 7/2/2024 Approved TIMOTHY POWELL
METHANE-Final 7/2/2024 Approved TIMOTHY POWELL
METHANE-Rough 7/2/2024 Approved TIMOTHY POWELL
Reinforced Concrete Frame 7/2/2024 Approved TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 7/2/2024 SGSOV Approved TIMOTHY POWELL
Smoke Detectors 7/2/2024 Approved TIMOTHY POWELL
Wood Frame 7/2/2024 Approved TIMOTHY POWELL
Final 8/7/2024 OK to Issue CofO TIMOTHY POWELL