901 N VINE ST 90038
Certificate Information: 901 N VINE ST 90038
- Application / Permit
- 22016-20000-14241
- Plan Check / Job No.
- B22VN07222
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) 21'-1.5" X 36'-8", 18'-10" X 36'-8" & 30'-3" X 36'-8" IRREGULAR SHAPED PORTION OF GARAGE AT 1ST FLOOR TO (3) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(C). ALL WORK PER ENGINEERING. SEE COMMENTS.
- Permit Issued
- Issued on 1/6/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | RAPHAEL ROSAS |
| Disabled Access Plans Picked Up | 6/3/2022 | APPLICANT |
| Corrections Issued | 6/6/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 6/13/2022 | STEVEN KIM |
| Building Plans Picked Up | 6/13/2022 | APPLICANT |
| Green Plans Picked Up | 6/13/2022 | APPLICANT |
| Applicant returned to address corrections | 11/17/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 12/7/2022 | RAPHAEL ROSAS |
| Issued | 1/6/2023 | APPLICANT |
| CofO in Progress | 8/7/2024 | TIMOTHY POWELL |
| CofO Issued | 8/8/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 8/8/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2022 | JEANIE LAM |
| Sewer availability | Cleared | 7/7/2022 | JEANIE LAM |
| "D" conditions | Cleared | 7/20/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 7/20/2022 | ANACANY HURTADO |
| ZI | Cleared | 7/20/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 7/22/2022 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2022 | JEANIE LAM |
| DAS Clearance | Cleared | 10/17/2022 | OLLIE CARTER |
| Fire Marshal Fire Life Safety | Cleared | 11/28/2022 | RONILO MULAWIN |
| Green Code | Cleared | 11/29/2022 | MICHAEL AYERS |
Contact Information
| Contractor | Hy-Max Building Corp; Lic. No.: 702339-B | 425 W BROADWAY #410 GLENDALE, CA 91204 |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Masonry | 1/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Pre-Inspection | 2/3/2023 | Approved | RONALD JIMENEZ |
| Reinforced Masonry Frame | 2/3/2023 | Partial Approval | RONALD JIMENEZ |
| Masonry Wall/Backfill | 2/23/2023 | Partial Approval | VAHE KELEDJIAN |
| Reinforced Masonry Frame | 2/23/2023 | Partial Approval | VAHE KELEDJIAN |
| Masonry Wall/Backfill | 3/9/2023 | Partial Approval | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 7/27/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 8/8/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Special/Order Compliance | 9/12/2023 | Approved | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Conditional Approval | VAHE KELEDJIAN |
| Light Gage Steel Frame | 10/11/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Special/Order Compliance | 10/25/2023 | Approved | RONALD JIMENEZ |
| Pre-Inspection | 1/17/2024 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 2/22/2024 | Approved | JEROME BLACKWOOD |
| Insulation | 2/27/2024 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 3/1/2024 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 3/6/2024 | Partial Approval | TIMOTHY POWELL |
| Insulation | 3/8/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 3/11/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 3/13/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 3/19/2024 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 4/12/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 4/18/2024 | Approved | TIMOTHY POWELL |
| Pre-Inspection | 6/21/2024 | Approved | TIMOTHY POWELL |
| Final | 7/2/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Green Building Final | 7/2/2024 | Approved | TIMOTHY POWELL |
| Green Building Rough | 7/2/2024 | Approved | TIMOTHY POWELL |
| METHANE-Final | 7/2/2024 | Approved | TIMOTHY POWELL |
| METHANE-Rough | 7/2/2024 | Approved | TIMOTHY POWELL |
| Reinforced Concrete Frame | 7/2/2024 | Approved | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | TIMOTHY POWELL |
| Smoke Detectors | 7/2/2024 | Approved | TIMOTHY POWELL |
| Wood Frame | 7/2/2024 | Approved | TIMOTHY POWELL |
| Final | 8/7/2024 | OK to Issue CofO | TIMOTHY POWELL |