2100 W 3RD ST STE 301 90057
Certificate Information: 2100 W 3RD ST STE 301 90057
- Application / Permit
- 22016-20000-14195
- Plan Check / Job No.
- B22VN07202
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- CHG OF USE FROM MEDICAL OFFICE TO DENTAL OFFICE
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | SEAN SHAHMIRI |
| Corrections Issued | 6/6/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 6/17/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/27/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 6/27/2022 | APPLICANT |
| Green Plans Picked Up | 6/27/2022 | APPLICANT |
| Plan Check Approved | 9/12/2022 | SEAN SHAHMIRI |
| Issued | 9/12/2022 | APPLICANT |
| CofO in Progress | 2/27/2023 | KATY RAMIREZ |
| CofO Issued | 3/1/2023 | ERNESTO CORRAL |
| Permit Finaled | 3/1/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 7/5/2022 | MICHAEL AYERS |
| Miscellaneous | Cleared | 7/7/2022 | DANG NGUYEN |
| ZA Case | Cleared | 7/7/2022 | DANG NGUYEN |
| ZA Case | Cleared | 7/7/2022 | DANG NGUYEN |
| Redevelopment Project Area | Cleared | 7/11/2022 | GRACIELA ACOSTA |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 7/29/2022 | AMAAN MALIK |
| DAS Clearance | Cleared | 8/29/2022 | SEAN SHAHMIRI |
Contact Information
| Architect | Balian,, David; Lic. No.: C33779 | 515 S. FIGUEROA ST.#1970 LOS ANGELES, CA 90071 |
| Contractor | J A Urban Inc; Lic. No.: 1034729-B | 702 S PRIMROSE AVE MONROVIA, CA 91016 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 10/5/2022 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 10/20/2022 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 11/21/2022 | No Access for Inspection | RAFAEL ESPINOZA |
| T-Bar Ceiling | 11/21/2022 | No Access for Inspection | RAFAEL ESPINOZA |
| Drywall Nailing | 11/22/2022 | Partial Approval | RONALD JIMENEZ |
| T-Bar Ceiling | 11/22/2022 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 11/29/2022 | Conditional Approval | DARRYL ARNOLD |
| T-Bar Ceiling | 11/29/2022 | Corrections Issued | DARRYL ARNOLD |
| T-Bar Ceiling | 12/5/2022 | Partial Approval | RONALD JIMENEZ |
| T-Bar Ceiling | 12/13/2022 | Partial Approval | KATY RAMIREZ |
| Green Building Final | 2/6/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Pre-Inspection | 2/6/2023 | Corrections Issued | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 2/6/2023 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 2/6/2023 | Approved | KATY RAMIREZ |
| Final | 2/17/2023 | Partial Inspection | KATY RAMIREZ |
| Green Building Final | 2/17/2023 | Approved | KATY RAMIREZ |
| Final | 2/27/2023 | OK to Issue CofO | KATY RAMIREZ |