751 E VERNON AVE 90291
Certificate Information: 751 E VERNON AVE 90291
- Application / Permit
- 22016-20000-13957
- Plan Check / Job No.
- B22VN07065
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING DETACHED 20'-3" X 21'-0" GARAGE AND UNPERMITTED 7'-4" x 14'-6" STRUCTURE BUILT PRIOR TO JANUARY 1, 2018 TO AN ACCESSORY DWELLING UNIT PER 65852.23. ALL WORK PER ENGINEER EXISTING CONSTRUCTION THAT DOES NOT POSE A THREAT TO THE PUBLIC'S HEALTH AND SAFETY WAS ALLOWED PER GOVERNMENT CODE SECTION 55.852.2(d)(2).
- Permit Issued
- Issued on 8/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 5/31/2022 | DANIEL ABRAMYAN |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| Applicant returned to address corrections | 3/28/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 4/15/2024 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 5/13/2024 | GIOVANNY CHAVEZ |
| Issued | 8/16/2024 | APPLICANT |
| CofO in Progress | 5/27/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 5/27/2025 | RICHARD STEINBACH |
| CofO Issued | 5/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 6/11/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | JOSE HERNANDEZ |
| ZI | Cleared | 6/13/2022 | MIGUEL GAMBOA |
| Specific Plan | Cleared | 7/6/2022 | VALERIA CEJA |
| Specific Plan | Cleared | 11/28/2022 | MIGUEL GAMBOA |
| Coastal Zone | Cleared | 3/21/2024 | ASHLEY RODARTE |
| Coastal Zone | Cleared | 3/21/2024 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 3/21/2024 | ASHLEY RODARTE |
| Specific Plan | Cleared | 3/21/2024 | ASHLEY RODARTE |
| ZI | Cleared | 3/21/2024 | ASHLEY RODARTE |
Contact Information
| Contractor | Unitech Construction Group Inc; Lic. No.: 953578-B | 13351-D RIVERSIDE DRIVE UNIT 450 SHERMAN OAKS, CA 91423 |
| Engineer | Hajdari,, Genti; Lic. No.: C88031 | 140 S MENTOR AVE APT #207 PASADENA, CA 91106 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/21/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 11/1/2024 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 12/17/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 12/19/2024 | Corrections Issued | HERBERT GIRON |
| Underground Mechanical | 12/23/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/31/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Rough | 12/31/2024 | Corrections Issued | MICHAEL ALLEN |
| Green Building Rough | 12/31/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| HVAC-Rough | 12/31/2024 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Rough | 12/31/2024 | Corrections Issued | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 1/3/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 1/3/2025 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Rough | 1/3/2025 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 1/3/2025 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 1/14/2025 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 1/14/2025 | Approved | HERBERT GIRON |
| Green Building Rough | 1/14/2025 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 1/14/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 1/24/2025 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Rough | 1/24/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 1/31/2025 | Corrections Issued | HERBERT GIRON |
| Sewer | 1/31/2025 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/5/2025 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 2/5/2025 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/21/2025 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 2/21/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/21/2025 | Partial Approval | HERBERT GIRON |
| Insulation | 2/25/2025 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Approved | HERBERT GIRON |
| Light Gage Steel Frame | 3/5/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/7/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 3/24/2025 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 3/24/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 3/25/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/7/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 5/7/2025 | Approved | JESUS RODRIGUEZ |
| Final | 5/7/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 5/7/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 5/7/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 5/7/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/7/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 5/7/2025 | Approved | JESUS RODRIGUEZ |
| Final | 5/27/2025 | OK to Issue CofO | JESUS RODRIGUEZ |