13106 N FENTON AVE 91342

Certificate Information: 13106 N FENTON AVE 91342

Application / Permit
22016-20000-13686
Plan Check / Job No.
B22VN06900
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT A 6' x 18' 6" 111 SQ. FT. PORTION OF THE (E) GARAGE INTO A (N) WASHROOM AND FULL BATHROOM.
Permit Issued
Issued on 5/31/2022
Issuing Office
Current Status
CofO Issued on 12/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 ALEC MOUSAKHANIAN
Corrections Issued 5/5/2022 ALEC MOUSAKHANIAN
Plan Check Approved 5/19/2022 ALEC MOUSAKHANIAN
Building Plans Picked Up 5/19/2022 APPLICANT
Issued 5/31/2022 APPLICANT
CofO in Progress 12/23/2022 ARAM AVEDISIAN
Permit Finaled 12/28/2022 MICHAEL SMITH
CofO Issued 12/28/2022 MICHAEL SMITH
Permit Finaled 12/28/2022 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/24/2022 Partial Approval ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 7/20/2022 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 8/1/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 8/1/2022 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 8/2/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 8/2/2022 Approved ARAM AVEDISIAN
HVAC-Final 8/2/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/2/2022 Approved ARAM AVEDISIAN
Drywall Nailing 8/10/2022 Partial Approval MISAEL ESPARZA
Insulation 8/10/2022 Partial Approval MISAEL ESPARZA
Drywall Nailing 9/29/2022 Approved ARAM AVEDISIAN
Final 12/14/2022 Corrections Issued ARAM AVEDISIAN
Smoke Detectors 12/14/2022 Not Ready for Inspection ARAM AVEDISIAN
Final 12/19/2022 No Access for Inspection ARAM AVEDISIAN
Smoke Detectors 12/19/2022 No Access for Inspection ARAM AVEDISIAN
Final 12/23/2022 OK to Issue CofO ARAM AVEDISIAN
PLUMBING-Final 12/23/2022 Approved ARAM AVEDISIAN
Smoke Detectors 12/23/2022 Approved ARAM AVEDISIAN