13106 N FENTON AVE 91342
Certificate Information: 13106 N FENTON AVE 91342
- Application / Permit
- 22016-20000-13686
- Plan Check / Job No.
- B22VN06900
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT A 6' x 18' 6" 111 SQ. FT. PORTION OF THE (E) GARAGE INTO A (N) WASHROOM AND FULL BATHROOM.
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Current Status
- CofO Issued on 12/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 5/5/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 5/19/2022 | ALEC MOUSAKHANIAN |
| Building Plans Picked Up | 5/19/2022 | APPLICANT |
| Issued | 5/31/2022 | APPLICANT |
| CofO in Progress | 12/23/2022 | ARAM AVEDISIAN |
| Permit Finaled | 12/28/2022 | MICHAEL SMITH |
| CofO Issued | 12/28/2022 | MICHAEL SMITH |
| Permit Finaled | 12/28/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/24/2022 | Partial Approval | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 7/20/2022 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 8/1/2022 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 8/1/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/2/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/2/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 8/2/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/2/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 8/10/2022 | Partial Approval | MISAEL ESPARZA |
| Insulation | 8/10/2022 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 9/29/2022 | Approved | ARAM AVEDISIAN |
| Final | 12/14/2022 | Corrections Issued | ARAM AVEDISIAN |
| Smoke Detectors | 12/14/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 12/19/2022 | No Access for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 12/19/2022 | No Access for Inspection | ARAM AVEDISIAN |
| Final | 12/23/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| PLUMBING-Final | 12/23/2022 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 12/23/2022 | Approved | ARAM AVEDISIAN |