4161 N PALMERO DR 90065
Certificate Information: 4161 N PALMERO DR 90065
- Application / Permit
- 22016-20000-13680
- Plan Check / Job No.
- B22VN06894
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE 20'-1" X 19'-3" (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | ANGELICA DAVE |
| Corrections Issued | 5/27/2022 | ANGELICA DAVE |
| Building Plans Picked Up | 6/1/2022 | APPLICANT |
| Plan Check Approved | 7/20/2022 | ANGELICA MARTINEZ |
| Issued | 7/22/2022 | APPLICANT |
| CofO in Progress | 2/29/2024 | HAMIK HARTOUNIAN |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
| CofO Issued | 3/8/2024 | DEROLD HAUFF |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/2/2022 | LANNY MERRICK |
| Address approval | Cleared | 6/7/2022 | CINDY QI |
| Sewer availability | Cleared | 6/7/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2022 | CINDY QI |
| Specific Plan | Cleared | 7/5/2022 | NASHYA JENSEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hajdari,, Genti; Lic. No.: C88031 | 140 S MENTOR AVE APT #207 PASADENA, CA 91106 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/4/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/14/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/14/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/5/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/5/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/16/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/16/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Special/Order Compliance | 1/20/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/6/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/6/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/23/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 2/23/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/23/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/23/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 2/23/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 2/23/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/28/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/28/2023 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 2/28/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/10/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 3/10/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/10/2023 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 3/10/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/20/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 3/20/2023 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 3/20/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 3/22/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 3/22/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Drywall Nailing | 3/28/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 1/24/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 1/24/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/24/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 2/28/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/28/2024 | Approved | HAMIK HARTOUNIAN |