CONVERT (E) 19' 7" X 20' 1" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT GCS65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 10/24/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2022 APPLICANT
Assigned to Plan Check Engineer 5/9/2022 MOHAMMAD ESMAILI
Corrections Issued 5/10/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 7/7/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 7/23/2022 GURUNATH NESARAJAH
Building Plans Picked Up 7/27/2022 APPLICANT
Plan Check Approved 8/17/2022 LUISANGEL VALENZUELA
Issued 10/24/2022 APPLICANT
CofO in Progress 8/1/2024 ROBERT NILES
Permit Finaled 5/23/2025 DANIEL SANCHEZ
CofO Issued 5/23/2025 DANIEL SANCHEZ
Permit Finaled 5/23/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 6/18/2022 STEVEN JIN
Roof/Waste drainage to street Cleared 6/18/2022 STEVEN JIN
Sewer availability Cleared 6/18/2022 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 6/29/2022 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 7/24/2022 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Abedian,, Vanik; Lic. No.: S5323 2906 JOLLEY DR      BURBANK, CA 91504

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/1/2022 Approved JOHN TCHANG
Footing/Foundation/Slab 12/12/2022 Corrections Issued JOHN TCHANG
PLUMBING-Rough 12/12/2022 Partial Approval JOHN TCHANG
Footing/Foundation/Slab 12/15/2022 Approved JOHN TCHANG
Deputy Reinf. Concrete 12/16/2022 Partial Approval JOEL WILLIAMS
ELECTRICAL-Rough 7/28/2023 Conditional Approval RUBEN PEREZ
HVAC-Rough 7/28/2023 Approved RUBEN PEREZ
PLUMBING-Rough 7/28/2023 Conditional Approval RUBEN PEREZ
Wood Frame 7/28/2023 Approved RUBEN PEREZ
PLUMBING-Rough 11/13/2023 Partial Approval ROBERT NILES
Sewer 1/18/2024 Corrections Issued ROBERT NILES
Sewer 1/19/2024 Approved ROBERT NILES
Interior/Exterior Lathing 2/13/2024 Approved RUBEN PEREZ
Sewer 2/13/2024 Approved RUBEN PEREZ
Insulation 3/20/2024 Approved RUBEN PEREZ
Shower Pan 3/20/2024 Approved RUBEN PEREZ
Drywall Nailing 3/28/2024 Approved PETER RUBIO
Interior/Exterior Lathing 3/28/2024 Approved PETER RUBIO
BUILDING-Rough-Frame 7/9/2024 Approved ROBERT NILES
Final 7/9/2024 Corrections Issued ROBERT NILES
Green Building Final 7/9/2024 Not Ready for Inspection ROBERT NILES
Green Building Rough 7/9/2024 Approved ROBERT NILES
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Approved ROBERT NILES
Smoke Detectors 7/9/2024 Not Ready for Inspection ROBERT NILES
Final 7/22/2024 Corrections Issued ROBERT NILES
Green Building Final 7/22/2024 Approved ROBERT NILES
Smoke Detectors 7/22/2024 Approved ROBERT NILES
Final 7/31/2024 OK to Issue CofO ROBERT NILES