6051 W GUTHRIE AVE 90034

Certificate Information: 6051 W GUTHRIE AVE 90034

Application / Permit
22016-20000-13585
Plan Check / Job No.
B22VN06831
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19' X 18' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 11/21/2022
Issuing Office
Current Status
CofO Issued on 6/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 PINANK PATEL
Corrections Issued 5/27/2022 PINANK PATEL
Building Plans Picked Up 6/1/2022 APPLICANT
Plan Check Approved 11/16/2022 MADISON ODELL
Issued 11/21/2022 APPLICANT
CofO in Progress 6/16/2025 ARTHUR NEGRETE
Permit Finaled 6/17/2025 DEROLD HAUFF
CofO Issued 6/17/2025 DEROLD HAUFF
Permit Finaled 6/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/28/2022 JEANIE LAM
Sewer availability Cleared 6/28/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/29/2022 JEANIE LAM
Construction near power lines Cleared 10/17/2022 RIDWAN HARDY
Construction within easement Cleared 11/16/2022 JOHN BACON

Contact Information

Contractor Makeover Builders Inc; Lic. No.: 986740-B 21781 VENTURA BLVD UNIT 634      WOODLAND HILLS, CA 91364

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/14/2022 Partial Approval JOSE AVILA
Underground Mechanical 12/19/2022 Partial Approval JOSE AVILA
ELECTRICAL-Rough 1/17/2023 Corrections Issued SCOTT FINNILA
HVAC-Rough 1/17/2023 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 1/17/2023 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 1/18/2023 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 1/18/2023 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/18/2023 Partial Approval SCOTT FINNILA
Green Building Rough 1/18/2023 Approved SCOTT FINNILA
HVAC-Rough 1/18/2023 Approved SCOTT FINNILA
PLUMBING-Rough 1/18/2023 Approved SCOTT FINNILA
Interior/Exterior Lathing 1/24/2023 Partial Approval ALEJANDRO DE ARTOLA
Insulation 1/26/2023 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 1/30/2023 Approved JOSE AVILA
Drywall Nailing 2/9/2023 Approved DONALD CRICHLOW
Interior/Exterior Lathing 2/9/2023 Approved DONALD CRICHLOW
Shower Pan 2/9/2023 Approved DONALD CRICHLOW
Final 6/12/2023 Corrections Issued JOSE AVILA
Green Building Final 6/12/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 6/12/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 6/12/2023 Approved JOSE AVILA
ELECTRICAL-Final 6/11/2025 No Access for Inspection ARTHUR NEGRETE
Final 6/11/2025 No Access for Inspection ARTHUR NEGRETE
HVAC-Final 6/11/2025 No Access for Inspection ARTHUR NEGRETE
PLUMBING-Final 6/11/2025 No Access for Inspection ARTHUR NEGRETE
ELECTRICAL-Final 6/13/2025 Approved ARTHUR NEGRETE
Final 6/13/2025 OK to Issue CofO ARTHUR NEGRETE
Grading Pre-Inspection 6/13/2025 Approved ARTHUR NEGRETE
HVAC-Final 6/13/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 6/13/2025 Approved ARTHUR NEGRETE