20650-20654 W COVELLO ST 91306
Certificate Information: 20650-20654 W COVELLO ST 91306
- Application / Permit
- 22016-20000-13469
- Plan Check / Job No.
- B22VN06788
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT ATTACHED 2-CAR GARAGE TO ADU (400 sq ft). CONVERT PORTION OF SFD TO JADU (236 sq ft). ADD [5'-6" 11'-7"] BATHROOM TO REAR BEDROOM OF (E) SFD. PROVIDE TWO OPEN PARKING SPACES.
- Permit Issued
- Issued on 7/21/2022
- Issuing Office
- Current Status
- CofO Corrected on 1/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2022 | JESSE JIMENEZ |
| Corrections Issued | 5/12/2022 | JESSE JIMENEZ |
| Applicant returned to address corrections | 6/13/2022 | JESSE JIMENEZ |
| Applicant returned to address corrections | 6/27/2022 | JESSE JIMENEZ |
| Plan Check Approved | 7/21/2022 | JESSE JIMENEZ |
| Issued | 7/21/2022 | APPLICANT |
| CofO in Progress | 11/18/2022 | STEVEN BACK |
| CofO Issued-Status Void | 11/23/2022 | JOHN JANSON |
| Permit Finaled-Status Void | 11/23/2022 | JOHN JANSON |
| Re-Activate Permit | 1/30/2023 | JOHN JANSON |
| Re-Activate Permit | 1/30/2023 | JOHN JANSON |
| CofO Corrected-Status Void | 1/30/2023 | JOHN JANSON |
| Permit Finaled-Status Void | 1/30/2023 | JOHN JANSON |
| Permit Finaled | 1/30/2023 | JOHN JANSON |
| CofO Corrected | 1/30/2023 | JOHN JANSON |
| Permit Finaled | 1/30/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/18/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2022 | ROMAN GUTIERREZ |
| Public Works-Highway Ded. | Cleared | 5/19/2022 | ROMAN GUTIERREZ |
| Public Works-Open Permits | Cleared | 5/19/2022 | ROMAN GUTIERREZ |
| Public Works-Sewers | Cleared | 5/19/2022 | ROMAN GUTIERREZ |
| Miscellaneous | Cleared | 7/20/2022 | JESSE JIMENEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/27/2022 | Corrections Issued | STEVEN BACK |
| Pre-Inspection | 7/27/2022 | Corrections Issued | STEVEN BACK |
| Sewer | 7/27/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 8/4/2022 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 8/4/2022 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 8/4/2022 | Corrections Issued | STEVEN BACK |
| Shower Pan | 8/4/2022 | Corrections Issued | STEVEN BACK |
| Deputy Drilled-In Anchors | 8/8/2022 | Conditional Approval | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 8/23/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 8/23/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 8/23/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 8/26/2022 | Partial Approval | STEVEN BACK |
| Interior/Exterior Lathing | 8/26/2022 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 9/1/2022 | Corrections Issued | STEVEN BACK |
| Insulation | 9/1/2022 | Partial Approval | STEVEN BACK |
| Interior/Exterior Lathing | 9/1/2022 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 9/9/2022 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 9/16/2022 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 9/16/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 9/16/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 9/16/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 9/21/2022 | Approved | STEVEN BACK |
| Green Building Rough | 9/21/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 9/21/2022 | Corrections Issued | STEVEN BACK |
| Shower Pan | 9/21/2022 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 9/26/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 9/26/2022 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 9/26/2022 | Partial Approval | DAVID SCANTLIN |
| Interior/Exterior Lathing | 9/26/2022 | Partial Approval | DAVID SCANTLIN |
| Shower Pan | 9/26/2022 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 10/14/2022 | Approved | STEVEN BACK |
| Final | 10/14/2022 | Not Ready for Inspection | STEVEN BACK |
| Footing/Foundation/Slab | 10/14/2022 | Approved | STEVEN BACK |
| Gas Test | 10/14/2022 | Not Ready for Inspection | STEVEN BACK |
| Green Building Final | 10/14/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Final | 10/14/2022 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 10/14/2022 | Corrections Issued | STEVEN BACK |
| Final | 11/1/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 11/1/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/1/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 11/1/2022 | Not Ready for Inspection | STEVEN BACK |
| Final | 11/10/2022 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 11/10/2022 | Approved | STEVEN BACK |
| Final | 11/18/2022 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | STEVEN BACK |