10255 N MATHER AVE 91040
Certificate Information: 10255 N MATHER AVE 91040
- Application / Permit
- 22016-20000-13300
- Plan Check / Job No.
- B22VN06706
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* REMODEL OF (E) 1-STORY SFD. COMPLY WITH DEPARTMENT ORDER effective date 05/06/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE 1- CHANGE OUT ALL EXTERIOR WINDOWS SAME SIZE SAME PLACE 2- INFILL ONE WINDOW (KITCHEN NORTH WALL) 3-INTERIOR REMODEL 4-REDO ELECTRIC AND PLUMBING 5-ATTIC INSULATION
- Permit Issued
- Issued on 5/25/2022
- Issuing Office
- Current Status
- Permit Finaled on 6/28/2023
Permit Application Status History
| Submitted | 5/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2022 | VIVIAN LAO |
| Corrections Issued | 5/3/2022 | VIVIAN LAO |
| Plan Check Approved | 5/19/2022 | VIVIAN LAO |
| Issued | 5/25/2022 | APPLICANT |
| Permit Finaled | 6/27/2023 | DAVID ANDERSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/4/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 5/17/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hagopyan,, Edmond; Lic. No.: C80143 | 7939 WENTWORTH STREET SUNLAND, CA 91040 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/1/2022 | Approved | EMIL ALEXANDRIAN |
| Wood Frame | 6/1/2022 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| ELECTRICAL-Rough | 6/28/2022 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 6/28/2022 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 6/28/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Wood Frame | 6/28/2022 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 6/29/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/29/2022 | Conditional Approval | DAVID ANDERSON |
| Wood Frame | 6/29/2022 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 7/5/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/5/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 7/5/2022 | Approved | DAVID ANDERSON |
| Shower Pan | 7/5/2022 | Approved | DAVID ANDERSON |
| Wood Frame | 7/5/2022 | Conditional Approval | DAVID ANDERSON |
| Insulation | 7/11/2022 | Approved | DAVID ANDERSON |
| Drywall Nailing | 7/13/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/13/2022 | Off-Hour Fees Due | |
| Final | 6/27/2023 | Permit Finaled | DAVID ANDERSON |
| Green Building Final | 6/27/2023 | Approved | DAVID ANDERSON |
| Smoke Detectors | 6/27/2023 | Approved | DAVID ANDERSON |