16250-16252 W MAYALL ST 91343

Certificate Information: 16250-16252 W MAYALL ST 91343

Application / Permit
22016-20000-13230
Plan Check / Job No.
B22VN06654
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) TWO-CAR GARAGE AND BREEZEWAY INTO ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e), AND 3'11" X 10' ADDITION. WORK PER ENGINEER.
Permit Issued
Issued on 9/9/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 ROSENDO MEDINA
Corrections Issued 5/7/2022 ROSENDO MEDINA
Building Plans Picked Up 7/7/2022 APPLICANT
Plan Check Approved 9/9/2022 LUIS RINCON
Issued 9/9/2022 APPLICANT
CofO in Progress 1/6/2023 CHRISTOPHER DELLEFIELD
Permit Finaled 1/21/2023 MICHAEL SMITH
CofO Issued 1/21/2023 MICHAEL SMITH
Permit Finaled 1/21/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/13/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 5/13/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 5/13/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 5/16/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Lobana,, Singh Maninder Pa; Lic. No.: C50989 885 PATRIOT DR #G      MOORPARK, CA 93021

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/20/2022 Corrections Issued JAVIER RAMOS JR
Sewer 9/20/2022 Partial Approval JAVIER RAMOS JR
Special/Order Compliance 9/20/2022 Corrections Issued JAVIER RAMOS JR
Deputy Drilled-In Anchors 9/23/2022 Conditional Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 9/28/2022 Approved DEANDRE HOFFMAN
Footing/Foundation/Slab 9/28/2022 Corrections Issued DEANDRE HOFFMAN
PLUMBING-Rough 9/28/2022 Partial Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 9/30/2022 Approved DEANDRE HOFFMAN
Deputy Wood Construction 10/21/2022 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Approved JAVIER RAMOS JR
Insulation 10/24/2022 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 10/31/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 10/31/2022 Approved JAVIER RAMOS JR
Gas Test 10/31/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 10/31/2022 Approved JAVIER RAMOS JR
HVAC-Rough 10/31/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/31/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 10/31/2022 Approved JAVIER RAMOS JR
Shower Pan 10/31/2022 Not Ready for Inspection JAVIER RAMOS JR
Wood Frame 10/31/2022 Approved JAVIER RAMOS JR
Insulation 11/2/2022 Approved JAVIER RAMOS JR
Drywall Nailing 11/7/2022 Approved CALEB MEISTER
ELECTRICAL-Final 12/7/2022 Not Ready for Inspection JAVIER RAMOS JR
Final 12/7/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 12/7/2022 Approved JAVIER RAMOS JR
Green Building Final 12/7/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 12/7/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 12/7/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 12/7/2022 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 12/14/2022 Approved JAVIER RAMOS JR
Final 12/14/2022 Partial Approval JAVIER RAMOS JR
Green Building Final 12/14/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 12/14/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/14/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 12/14/2022 Approved JAVIER RAMOS JR
Final 1/6/2023 OK to Issue CofO CHRISTOPHER DELLEFIELD