450 N SKYEWIAY ROAD 90049
Certificate Information: 450 N SKYEWIAY ROAD 90049
- Application / Permit
- 22016-20000-13209
- Plan Check / Job No.
- B22VN06626
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR AND EXTERIOR REMODEL TO THE (E) TWO STORY SFD PER ENGINEERING.
- Permit Issued
- Issued on 7/12/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/12/2023
Permit Application Status History
| Submitted | 4/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/15/2022 | APPLICANT |
| Plan Check Approved | 7/5/2022 | ARTIN ZARUKIAN |
| Issued | 7/12/2022 | APPLICANT |
| Permit Finaled | 1/11/2023 | KEVIN SARGSYAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/22/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/29/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/19/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 9/19/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/20/2022 | Partial Approval | JUAN VALENZUELA |
| HVAC-Rough | 9/20/2022 | Approved | JUAN VALENZUELA |
| Insulation | 9/23/2022 | Approved | JUAN VALENZUELA |
| Shower Pan | 9/23/2022 | Approved | JUAN VALENZUELA |
| Deputy Wood Construction | 9/27/2022 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 9/30/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/30/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 12/30/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 12/30/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 12/30/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 12/30/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 12/30/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 1/3/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 1/3/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 1/3/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 1/11/2023 | Approved | KEVIN SARGSYAN |
| Final | 1/11/2023 | Permit Finaled | KEVIN SARGSYAN |
| HVAC-Final | 1/11/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 1/11/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/11/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 1/11/2023 | Approved | KEVIN SARGSYAN |