5255 W ADAMS BLVD 90016
Certificate Information: 5255 W ADAMS BLVD 90016
- Application / Permit
- 22016-20000-13114
- Plan Check / Job No.
- B22VN06593
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT OF EXISTING RETAIL SPACE TO ADD NEW PARTITION WALLS, NEW COUNTERS, ADA RESTROOM , STORAGE AND OFFICES
- Permit Issued
- Issued on 2/16/2024
- Issuing Office
- Metro
- Current Status
- Issued on 2/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2022 | RARES BODEA |
| Corrections Issued | 6/27/2022 | RARES BODEA |
| Quality Review Completed | 6/29/2022 | STEVEN KIM |
| Building Plans Picked Up | 6/29/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 7/7/2022 | APPLICANT |
| Plan Check Approved | 2/8/2024 | RARES BODEA |
| Issued | 2/16/2024 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/29/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 7/29/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 7/29/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 7/29/2022 | DALIA MOKAYED |
| Sewer availability | Cleared | 8/1/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | TREVOR QUAN |
| DAS Clearance | Cleared | 8/30/2023 | NORLITO MEDRANO |
| Community Plan Implem. Overlay | Cleared | 1/18/2024 | KYLE WINSTON |
| Redevelopment Project Area | Cleared | 1/27/2024 | SUSAN WONG |
Contact Information
| Contractor | Lumens Electric And Construction Company; Lic. No.: 869803-B | 4975 NAVARRO STREET LOS ANGELES, CA 90032 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 7/24/2024 | Not Ready for Inspection | JACOB MYERS |
| Insulation | 7/24/2024 | Not Ready for Inspection | JACOB MYERS |
| Pre-Inspection | 7/24/2024 | Partial Inspection | JACOB MYERS |
| Insulation | 12/27/2024 | Partial Approval | RONALD JIMENEZ |
| Insulation | 10/1/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Insulation | 10/6/2025 | Approved | MARTIN TAVITIAN |
| Wood Frame | 10/6/2025 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 11/3/2025 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 3/3/2026 | Partial Approval | IAN BLINN |