6850-6852 N CLAIRE AVE 91335
Certificate Information: 6850-6852 N CLAIRE AVE 91335
- Application / Permit
- 22016-20000-13018
- Plan Check / Job No.
- B22VN06538
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* CONVERT (E) ATTACHED 2-CAR GARAGE TO ADU (417 SF) PER CA GC 65852.2(e)(1)(A). ALL CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Current Status
- CofO Issued on 3/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | VIVIAN LAO |
| Corrections Issued | 5/6/2022 | VIVIAN LAO |
| Plan Check Approved | 6/14/2022 | VIVIAN LAO |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 3/6/2024 | JEFFREY BULL |
| Permit Finaled | 3/21/2024 | JOHN JANSON |
| CofO Issued | 3/21/2024 | JOHN JANSON |
| Permit Finaled | 3/21/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/13/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/13/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2022 | CARLOS AGUILERA |
| ZI | Cleared | 5/16/2022 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/10/2023 | Partial Approval | SEAN HAUPT |
| Pre-Inspection | 7/10/2023 | Approved | SEAN HAUPT |
| Sewer | 7/10/2023 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 7/14/2023 | Partial Approval | JEFFREY BULL |
| Sewer | 7/14/2023 | Approved | JEFFREY BULL |
| Deputy Drilled-In Anchors | 7/18/2023 | Conditional Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 7/20/2023 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 8/2/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 8/16/2023 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Rough | 8/16/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 8/16/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 9/19/2023 | Approved | JEFFREY BULL |
| Insulation | 9/19/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/19/2023 | Partial Approval | JEFFREY BULL |
| Shower Pan | 9/19/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 9/28/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 9/28/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/28/2023 | Approved | JEFFREY BULL |
| Final | 2/2/2024 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 2/28/2024 | Approved | HENRY KIM |
| ELECTRICAL-Final | 2/28/2024 | Approved | HENRY KIM |
| Final | 2/28/2024 | Corrections Issued | HENRY KIM |
| Green Building Final | 2/28/2024 | Approved | HENRY KIM |
| HVAC-Final | 2/28/2024 | Approved | HENRY KIM |
| PLUMBING-Final | 2/28/2024 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 2/28/2024 | Approved | HENRY KIM |
| Final | 3/5/2024 | OK to Issue CofO | JEFFREY BULL |
| PLUMBING-Final | 3/5/2024 | Approved | JEFFREY BULL |