12883-12885 N BROMONT AVE 91340

Certificate Information: 12883-12885 N BROMONT AVE 91340

Application / Permit
22016-20000-13016
Plan Check / Job No.
B22VN06537
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* CONVERT EXISTING ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 1/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Corrections Issued 5/4/2022 SELLA BENYAMIN
Assigned to Plan Check Engineer 5/5/2022 SELLA BENYAMIN
Plan Check Approved 5/12/2022 SELLA BENYAMIN
Issued 5/17/2022 APPLICANT
CofO in Progress 12/27/2022 ARAM AVEDISIAN
Permit Finaled 1/12/2023 MICHAEL SMITH
CofO Issued 1/12/2023 MICHAEL SMITH
Permit Finaled 1/12/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/9/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/9/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/9/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/6/2022 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 6/7/2022 Conditional Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 6/13/2022 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 6/16/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 7/20/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 7/20/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Approved ARAM AVEDISIAN
HVAC-Rough 8/2/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/2/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 8/8/2022 Partial Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 8/16/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/16/2022 Partial Approval ARAM AVEDISIAN
Insulation 8/23/2022 Conditional Approval ARAM AVEDISIAN
Insulation 9/2/2022 Approved ROBERT GOLD
Drywall Nailing 9/8/2022 Approved CHRISTOPHER DELLEFIELD
Shower Pan 9/16/2022 Approved ARAM AVEDISIAN
Final 12/19/2022 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 12/19/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 12/27/2022 Approved ARAM AVEDISIAN
Final 12/27/2022 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 12/27/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 12/27/2022 Approved ARAM AVEDISIAN