4159 N CAMELLIA AVE 91604

Certificate Information: 4159 N CAMELLIA AVE 91604

Application / Permit
22016-20000-12913
Plan Check / Job No.
B22VN06481
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER DESIGN.
Permit Issued
Issued on 6/13/2022
Issuing Office
Current Status
CofO Issued on 1/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 ROSENDO MEDINA
Corrections Issued 5/5/2022 ROSENDO MEDINA
Applicant returned to address corrections 6/10/2022 ROSENDO MEDINA
Plan Check Approved 6/13/2022 ROSENDO MEDINA
Issued 6/13/2022 APPLICANT
Building Plans Picked Up 6/15/2022 APPLICANT
CofO in Progress 11/4/2022 JACK KARGODORIAN
CofO Issued 1/12/2023 MICHAEL SMITH
Permit Finaled 1/12/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/6/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/6/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/10/2022 DAGOVERTO GUERRERO

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Pearl Remodeling; Lic. No.: 955824-B 6803 YARMOUTH AVENUE      RESEDA, CA 91335

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/12/2022 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 7/15/2022 Partial Approval THOMAS FINNILA
Sewer 7/20/2022 Approved DAVID MATSON
Underground Mechanical 7/20/2022 Partial Approval DAVID MATSON
PLUMBING-Rough 8/4/2022 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 8/11/2022 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 8/11/2022 Corrections Issued CALEB MEISTER
Green Building Rough 8/11/2022 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 8/11/2022 Approved CALEB MEISTER
ELECTRICAL-Rough 8/23/2022 Approved CALEB MEISTER
Insulation 8/23/2022 Partial Approval CALEB MEISTER
Interior/Exterior Lathing 8/23/2022 Partial Approval CALEB MEISTER
BUILDING-Rough-Frame 8/29/2022 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Approved CALEB MEISTER
Green Building Rough 8/29/2022 Approved CALEB MEISTER
Insulation 8/29/2022 Approved CALEB MEISTER
Drywall Nailing 9/1/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 9/1/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 10/21/2022 Not Ready for Inspection JACK KARGODORIAN
Final 10/21/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 10/21/2022 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 10/21/2022 Approved JACK KARGODORIAN
PLUMBING-Final 10/21/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/21/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 10/21/2022 Approved JACK KARGODORIAN
Final 10/28/2022 OK to Issue CofO JACK KARGODORIAN
Green Building Final 10/28/2022 Approved JACK KARGODORIAN