1703 N CAMPUS ROAD 90041

Certificate Information: 1703 N CAMPUS ROAD 90041

Application / Permit
22016-20000-12869
Plan Check / Job No.
B22VN06450
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 13' X 23' IRR.-SHAPE GARAGE & PORTION OF SFD TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 7/28/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 GURUNATH NESARAJAH
Corrections Issued 5/6/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 6/22/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 7/25/2022 GURUNATH NESARAJAH
Building Plans Picked Up 7/26/2022 APPLICANT
Plan Check Approved 7/28/2022 ALEC MOUSAKHANIAN
Issued 7/28/2022 APPLICANT
CofO in Progress 9/29/2022 CRAIG VAUGHAN
CofO in Progress 9/29/2022 CRAIG VAUGHAN
Permit Finaled 11/29/2022 DEROLD HAUFF
CofO Issued 11/29/2022 DEROLD HAUFF
Permit Finaled 11/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/18/2022 STEVE MELGAR
Sewer availability Cleared 5/18/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 5/19/2022 STEVE MELGAR
Grading Pre-Inspection Cleared 6/2/2022 ROBERT HUGHES
Address approval Cleared 7/14/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Chiang,, Tzuu Pien; Lic. No.: C72618 18295 AGUIRO STREET      ROWLAND HEIGHTS, CA 91748

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/3/2022 Approved CRAIG VAUGHAN
Green Building Rough 8/3/2022 Approved CRAIG VAUGHAN
Wood Frame 8/3/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 8/9/2022 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 8/9/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 8/9/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 9/21/2022 Corrections Issued CRAIG VAUGHAN
Final 9/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 9/21/2022 Approved CRAIG VAUGHAN
Green Building Final 9/21/2022 Approved CRAIG VAUGHAN
HVAC-Final 9/21/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 9/21/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 9/21/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 9/28/2022 Approved CRAIG VAUGHAN
Final 9/28/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 9/28/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 9/28/2022 Approved CRAIG VAUGHAN
Smoke Detectors 9/28/2022 Approved CRAIG VAUGHAN