9170 N COLUMBUS AVE 91343

Certificate Information: 9170 N COLUMBUS AVE 91343

Application / Permit
22016-20000-12785
Plan Check / Job No.
B22VN06403
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 30'X20' GARAGE INTO ACCESSORY DWELLING UNIT W/6'7"X7'7" STORAGE ROOM (ACC FROM OUTSIDE ONLY) PER LAMC 12.22A.3(c) & (d) - ALL WORK PER ENGINEER
Permit Issued
Issued on 10/6/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 HAYATO TSUCHIYA
Corrections Issued 5/10/2022 HAYATO TSUCHIYA
Plan Check Approved 9/30/2022 DANIEL ABRAMYAN
Issued 10/6/2022 APPLICANT
CofO in Progress 6/21/2023 JUAN VALENZUELA
Permit Finaled 8/23/2024 DANIEL ORRANTE
CofO Issued 8/23/2024 DANIEL ORRANTE
Permit Finaled 8/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/30/2022 CHRIS CHAHBAZ
Miscellaneous Cleared 8/30/2022 CHRIS CHAHBAZ
Sewer availability Cleared 8/30/2022 CHRIS CHAHBAZ
Eng Process Fee Ord 176,300 Cleared 9/6/2022 CHRIS CHAHBAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 450 NORTH BRAND BLVD STE 600      GLENDALE, CA 91203

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/6/2022 Partial Approval CHRISTOPHER DELLEFIELD
Sewer 12/6/2022 Approved CHRISTOPHER DELLEFIELD
Gas Test 12/13/2022 Approved MICHEL ABAJAN
Underground Mechanical 12/13/2022 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 12/27/2022 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 12/29/2022 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 12/29/2022 Partial Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 1/20/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/30/2023 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 3/30/2023 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 4/11/2023 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 4/11/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 4/11/2023 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/11/2023 Approved CHRISTOPHER DELLEFIELD
Deputy Wood Construction 4/14/2023 Conditional Approval MICHAEL SMITH
BUILDING-Rough-Frame 4/17/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Deputy Wood Construction 4/17/2023 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 4/17/2023 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 4/17/2023 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/21/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 4/21/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/21/2023 Conditional Approval CHRISTOPHER DELLEFIELD
Insulation 4/26/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 5/5/2023 Approved CHRISTOPHER DELLEFIELD
Shower Pan 5/10/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/16/2023 Approved CHRISTOPHER DELLEFIELD
Final 6/13/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 6/13/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 6/13/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 6/20/2023 Approved JUAN VALENZUELA
Final 6/20/2023 OK to Issue CofO JUAN VALENZUELA
HVAC-Final 6/20/2023 Approved JUAN VALENZUELA
PLUMBING-Final 6/20/2023 Approved JUAN VALENZUELA