9170 N COLUMBUS AVE 91343
Certificate Information: 9170 N COLUMBUS AVE 91343
- Application / Permit
- 22016-20000-12785
- Plan Check / Job No.
- B22VN06403
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED 30'X20' GARAGE INTO ACCESSORY DWELLING UNIT W/6'7"X7'7" STORAGE ROOM (ACC FROM OUTSIDE ONLY) PER LAMC 12.22A.3(c) & (d) - ALL WORK PER ENGINEER
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 5/10/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 9/30/2022 | DANIEL ABRAMYAN |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 6/21/2023 | JUAN VALENZUELA |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
| CofO Issued | 8/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2022 | CHRIS CHAHBAZ |
| Miscellaneous | Cleared | 8/30/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 8/30/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | CHRIS CHAHBAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/6/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Sewer | 12/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 12/13/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 12/13/2022 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 12/27/2022 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 12/29/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 12/29/2022 | Partial Inspection | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 1/20/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 3/30/2023 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 3/30/2023 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/11/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 4/11/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/11/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 4/11/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 4/14/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 4/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 4/17/2023 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 4/17/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/17/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/21/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/21/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 4/26/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/5/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/16/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 6/13/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 6/13/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/13/2023 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 6/13/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 6/20/2023 | Approved | JUAN VALENZUELA |
| Final | 6/20/2023 | OK to Issue CofO | JUAN VALENZUELA |
| HVAC-Final | 6/20/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 6/20/2023 | Approved | JUAN VALENZUELA |