4190 S BUCKINGHAM ROAD 90008
Certificate Information: 4190 S BUCKINGHAM ROAD 90008
- Application / Permit
- 22016-20000-12566
- Plan Check / Job No.
- B22VN06262
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (7) Garage - Private
- Work Description
- CONVERT A PORTION OF THE (E) GARAGE INTO A (N) 289 SQFT ACCESSORY DWELLING UNIT AND ONE CAR GARAGE PER GCS 65852.2(e)(1)(D)
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Current Status
- CofO Issued on 8/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2022 | JEFFREY TANGONAN |
| Corrections Issued | 4/30/2022 | JEFFREY TANGONAN |
| Issued | 6/3/2022 | APPLICANT |
| Building Plans Picked Up | 6/9/2022 | APPLICANT |
| CofO in Progress | 8/14/2023 | DARRYL ARNOLD |
| Permit Finaled | 8/14/2023 | WINSTON DUNNING |
| CofO Issued | 8/14/2023 | WINSTON DUNNING |
| Permit Finaled | 8/14/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/5/2022 | MICHAEL SOTO |
| Address approval | Cleared | 5/6/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 5/6/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 5/6/2022 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 5/9/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2022 | JEANETTE VONG |
Contact Information
| Contractor | Lefert Maintenance Group Inc; Lic. No.: 1051028-B | 3325 WILSHIRE BOULEVARD #350 LOS ANGELES, CA 90010 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/10/2022 | Corrections Issued | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 11/14/2022 | Approved | TIMOTHY BUXTON |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Rough | 12/16/2022 | Not Ready for Inspection | ALAN MORELOS |
| Wood Frame | 12/16/2022 | Not Ready for Inspection | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Conditional Approval | DARRYL ARNOLD |
| Green Building Rough | 12/27/2022 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 12/27/2022 | Corrections Issued | DARRYL ARNOLD |
| Insulation | 1/3/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 1/3/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 1/5/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Special/Order Compliance | 1/5/2023 | Approved | EDWIN GREGORYONA |
| Wood Frame | 1/5/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Insulation | 1/9/2023 | Partial Approval | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 1/9/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 1/13/2023 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 1/13/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Interior/Exterior Lathing | 1/13/2023 | Approved | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 4/7/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Drywall Nailing | 5/30/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 5/30/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Green Building Final | 5/30/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Green Building Rough | 5/30/2023 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/30/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 5/30/2023 | Approved | DARRYL ARNOLD |
| Wood Frame | 5/30/2023 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 8/14/2023 | Approved | DARRYL ARNOLD |
| Final | 8/14/2023 | Conditional Approval | DARRYL ARNOLD |
| Green Building Final | 8/14/2023 | Approved | DARRYL ARNOLD |
| Green Building Rough | 8/14/2023 | Approved | DARRYL ARNOLD |
| METHANE-Final | 8/14/2023 | Approved | DARRYL ARNOLD |
| METHANE-Rough | 8/14/2023 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/14/2023 | SGSOV Approved | DARRYL ARNOLD |
| Wood Frame | 8/14/2023 | Approved | DARRYL ARNOLD |