8928-8930 N GOTHIC AVE 91343

Certificate Information: 8928-8930 N GOTHIC AVE 91343

Application / Permit
22016-20000-12445
Plan Check / Job No.
B22VN06214
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (372 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 6/24/2022
Issuing Office
Current Status
CofO Issued on 12/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2022 APPLICANT
Assigned to Plan Check Engineer 4/29/2022 JEROME MAGAT PALMA
Corrections Issued 4/30/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 6/23/2022 JEROME MAGAT PALMA
Plan Check Approved 6/24/2022 JEROME MAGAT PALMA
Issued 6/24/2022 APPLICANT
Building Plans Picked Up 6/24/2022 APPLICANT
CofO in Progress 9/29/2023 RAUL OLAGI
Permit Finaled 12/1/2023 RUBEN SALAS
CofO Issued 12/1/2023 RUBEN SALAS
Permit Finaled 12/1/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/3/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/3/2022 CARLOS AGUILERA
Sewer availability Cleared 5/3/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2022 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 11/28/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 11/28/2022 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 12/9/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 12/9/2022 Partial Approval RAUL OLAGI
Deputy Drilled-In Anchors 12/13/2022 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 12/15/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 12/27/2022 Corrections Issued RAUL OLAGI
HVAC-Rough 12/27/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 12/27/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 1/12/2023 Approved RAUL OLAGI
Green Building Rough 1/12/2023 Approved RAUL OLAGI
HVAC-Rough 1/12/2023 Partial Approval RAUL OLAGI
Insulation 1/12/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 1/12/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 1/23/2023 Approved RAUL OLAGI
Insulation 1/23/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 1/23/2023 Partial Approval RAUL OLAGI
Drywall Nailing 2/6/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 2/24/2023 Approved RAUL OLAGI
Final 4/3/2023 Corrections Issued RAUL OLAGI
Green Building Final 4/3/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/3/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 4/3/2023 Corrections Issued RAUL OLAGI
Final 5/4/2023 Corrections Issued RAUL OLAGI
Smoke Detectors 5/4/2023 Approved RAUL OLAGI
Final 9/29/2023 OK to Issue CofO RAUL OLAGI