2444 S BARRY AVE 90064
Certificate Information: 2444 S BARRY AVE 90064
- Application / Permit
- 22016-20000-12418
- Plan Check / Job No.
- B22VN06201
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- INSTALL STRUCTURAL SUPPORT FOR PROPOSED ROOF MOUNTED SOLAR WATER HEATING SYSTEM PER ENGINEER
- Permit Issued
- Issued on 3/22/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 12/21/2023
Permit Application Status History
| Submitted | 4/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 4/30/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| Applicant returned to address corrections | 11/4/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 2/10/2023 | RAMA DABADGE |
| Plan Check Approved | 3/22/2023 | OMAR GARNICA |
| Issued | 3/22/2023 | APPLICANT |
| Permit Finaled | 12/20/2023 | PAUL DAVIDSON |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/27/2022 | DANIEL CORONADO |
| Specific Plan | Cleared | 6/23/2022 | CONNIE CHAUV |
Contact Information
| Contractor | California Solar Integrators Inc; Lic. No.: 1004246-B | 200S SAN PEDRO ST #500 LOS ANGELES, CA 90012 |
| Engineer | Zandieh,, Arash; Lic. No.: C82118 | 3666 SILVER OAK PLACE DANVILLE, CA 94506 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 11/6/2023 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 11/6/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 12/13/2023 | Conditional Approval | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 12/13/2023 | Approved | DERRICK SPENCER |
| Final | 12/20/2023 | Permit Finaled | PAUL DAVIDSON |