16103 W LASSEN ST 91343

Certificate Information: 16103 W LASSEN ST 91343

Application / Permit
22016-20000-12370
Plan Check / Job No.
B22VN06180
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU addition. Existing Garage to be converted to new ADU (360 Sq. Ft.) + New Addition to new ADU (540 Sq. Ft.)
Permit Issued
Issued on 3/23/2023
Issuing Office
Current Status
Issued on 3/23/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/23/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 SELLA BENYAMIN
Corrections Issued 4/28/2022 SELLA BENYAMIN
Applicant returned to address corrections 12/14/2022 SELLA BENYAMIN
Plan Check Approved 3/6/2023 DANIEL YIP
Issued 3/23/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/4/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/5/2022 CARLOS AGUILERA
Sewer availability Cleared 5/11/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 5/13/2022 KIRK LINKLATER
Construction near power lines Cleared 6/21/2022 RIDWAN HARDY
Low Impact Development Cleared 12/28/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 12/29/2022 CARLOS AGUILERA
GPI Written Notices Cleared 3/6/2023 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/4/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 4/4/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 4/4/2023 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 5/17/2023 Conditional Approval JAVIER RAMOS JR
PLUMBING-Rough 5/17/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 5/26/2023 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 5/26/2023 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 5/26/2023 Not Ready for Inspection JAVIER RAMOS JR
Pre-Inspection 6/14/2023 Approved JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 6/14/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 6/26/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/26/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Approved JAVIER RAMOS JR
Green Building Rough 6/26/2023 Approved JAVIER RAMOS JR
HVAC-Rough 6/26/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 6/26/2023 Approved JAVIER RAMOS JR
Shower Pan 6/26/2023 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 7/27/2023 Not Ready for Inspection JAVIER RAMOS JR
Insulation 7/27/2023 Partial Inspection JAVIER RAMOS JR
HVAC-Rough 7/31/2023 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 7/31/2023 Partial Approval JAVIER RAMOS JR
Shower Pan 7/31/2023 Not Ready for Inspection JAVIER RAMOS JR
Wood Frame 7/31/2023 Not Ready for Inspection JAVIER RAMOS JR
Drywall Nailing 8/28/2023 No Access for Inspection KEVIN BERBERYAN
Drywall Nailing 9/12/2023 Approved ROBERT GOLD
Shower Pan 11/30/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/2/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 12/3/2023 Off-Hour Fees Due
Rough-Elec/Plmb/HVAC 12/11/2023 Partial Inspection MISAEL ESPARZA
Sewer 12/11/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 12/13/2023 Approved JAVIER RAMOS JR
HVAC-Rough 12/13/2023 Approved JAVIER RAMOS JR
Insulation 12/13/2023 Approved JAVIER RAMOS JR
Sewer 12/13/2023 Approved JAVIER RAMOS JR
Underground Mechanical 12/13/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Final 4/11/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 4/11/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 4/11/2024 Approved JAVIER RAMOS JR
Green Building Final 4/11/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 4/11/2024 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 4/11/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/11/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 4/11/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/3/2024 Approved JAVIER RAMOS JR
Final 5/3/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 5/3/2024 Approved JAVIER RAMOS JR
HVAC-Final 5/3/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 5/3/2024 Approved JAVIER RAMOS JR
Service/Power Release 5/3/2024 Not Ready for Inspection JAVIER RAMOS JR