16103 W LASSEN ST 91343
Certificate Information: 16103 W LASSEN ST 91343
- Application / Permit
- 22016-20000-12370
- Plan Check / Job No.
- B22VN06180
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU addition. Existing Garage to be converted to new ADU (360 Sq. Ft.) + New Addition to new ADU (540 Sq. Ft.)
- Permit Issued
- Issued on 3/23/2023
- Issuing Office
- Current Status
- Issued on 3/23/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | SELLA BENYAMIN |
| Corrections Issued | 4/28/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 12/14/2022 | SELLA BENYAMIN |
| Plan Check Approved | 3/6/2023 | DANIEL YIP |
| Issued | 3/23/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/11/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 5/13/2022 | KIRK LINKLATER |
| Construction near power lines | Cleared | 6/21/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/28/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 12/29/2022 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 3/6/2023 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/4/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/4/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/4/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/17/2023 | Conditional Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/17/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/26/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 5/26/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/26/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 6/14/2023 | Approved | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 6/14/2023 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/26/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/26/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 6/26/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/26/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/26/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/26/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 7/27/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 7/27/2023 | Partial Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 7/31/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/31/2023 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 7/31/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Wood Frame | 7/31/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 8/28/2023 | No Access for Inspection | KEVIN BERBERYAN |
| Drywall Nailing | 9/12/2023 | Approved | ROBERT GOLD |
| Shower Pan | 11/30/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/2/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 12/3/2023 | Off-Hour Fees Due | |
| Rough-Elec/Plmb/HVAC | 12/11/2023 | Partial Inspection | MISAEL ESPARZA |
| Sewer | 12/11/2023 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/13/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 12/13/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 12/13/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 12/13/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/11/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 4/11/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/11/2024 | Approved | JAVIER RAMOS JR |
| Green Building Final | 4/11/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 4/11/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Final | 4/11/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/11/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 5/3/2024 | Approved | JAVIER RAMOS JR |
| Final | 5/3/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 5/3/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 5/3/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 5/3/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 5/3/2024 | Not Ready for Inspection | JAVIER RAMOS JR |