1665 1/2 W 36TH PL 90018

Certificate Information: 1665 1/2 W 36TH PL 90018

Application / Permit
22016-20000-12329
Plan Check / Job No.
B22VN06162
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 20'-0" x 20'-0" DETACHED GARAGE (E) 20'-0" x 5'-0" STORAGE INTO A (N) DETACHED ACCESSORY DWELLING UNIT PER WFPP. ALL WORK TO COMPLY WITH GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 7/1/2022
Issuing Office
Current Status
CofO Issued on 5/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 ALFRED RAMIREZ
Corrections Issued 5/7/2022 ALFRED RAMIREZ
Issued 7/1/2022 APPLICANT
Building Plans Picked Up 7/7/2022 APPLICANT
CofO in Progress 8/23/2023 STUART CHAPMAN
CofO Issued 5/22/2024 DEROLD HAUFF
Permit Finaled 5/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/18/2022 STEVE MELGAR
Sewer availability Cleared 5/18/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 5/19/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/12/2022 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 7/18/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 8/29/2022 Approved SABAS ALONSO
Green Building Rough 8/29/2022 Not Ready for Inspection SABAS ALONSO
METHANE-Rough 8/29/2022 Approved SABAS ALONSO
PLUMBING-Rough 9/8/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 9/16/2022 Approved SABAS ALONSO
Green Building Rough 9/16/2022 Approved SABAS ALONSO
HVAC-Rough 9/27/2022 Approved SABAS ALONSO
Insulation 9/27/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/7/2022 Approved SABAS ALONSO
Drywall Nailing 12/9/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/9/2022 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 12/29/2022 Partial Approval SABAS ALONSO
Sewer 1/23/2023 Partial Approval SABAS ALONSO
Gas Test 5/5/2023 No Access for Inspection SABAS ALONSO
Sewer 5/5/2023 No Access for Inspection SABAS ALONSO
Final 5/17/2023 No Access for Inspection SABAS ALONSO
Green Building Final 5/17/2023 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/17/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 5/17/2023 No Access for Inspection SABAS ALONSO
Final 5/24/2023 No Access for Inspection SABAS ALONSO
Green Building Final 5/24/2023 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/24/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 5/24/2023 No Access for Inspection SABAS ALONSO
Final 6/1/2023 Corrections Issued STUART CHAPMAN
Green Building Final 6/1/2023 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 6/1/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 6/21/2023 Corrections Issued SABAS ALONSO
Final 6/21/2023 Corrections Issued SABAS ALONSO
Gas Test 6/21/2023 Corrections Issued SABAS ALONSO
Green Building Final 6/21/2023 Approved SABAS ALONSO
PLUMBING-Final 6/21/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/21/2023 SGSOV Not Ready SABAS ALONSO
ELECTRICAL-Final 7/6/2023 Not Ready for Inspection SABAS ALONSO
Gas Test 7/6/2023 Approved SABAS ALONSO
Final 8/14/2023 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 8/14/2023 SGSOV Approved SABAS ALONSO
Final 8/18/2023 OK to Issue CofO STUART CHAPMAN