648 N CHAUTAUQUA BLVD 90272
Certificate Information: 648 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 22016-20000-12324
- Plan Check / Job No.
- B22VN06159
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) ACCESSORY LIVING QUARTERS TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/17/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/24/2022 | STEVEN KIM |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| Plan Check Approved | 10/21/2022 | NILOOFAR MEHRAIN |
| Issued | 11/10/2022 | APPLICANT |
| CofO in Progress | 5/17/2023 | DANIEL ORRANTE |
| CofO in Progress | 5/18/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 5/30/2023 | DANIEL ORRANTE |
| CofO Issued | 5/30/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/30/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/27/2022 | DANIEL CORONADO |
| Miscellaneous | Cleared | 5/27/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 5/27/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 5/27/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 5/27/2022 | DANIEL CORONADO |
| Address approval | Cleared | 5/31/2022 | JENSON LEE |
| Sewer availability | Cleared | 5/31/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2022 | JENSON LEE |
| Hydrant and Access approval | Cleared | 10/11/2022 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/9/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Pre-Inspection | 3/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 4/6/2023 | Approved | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 4/6/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/13/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 4/27/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/27/2023 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 4/27/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 5/3/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 5/3/2023 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Final | 5/3/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 5/3/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 5/17/2023 | OK to Issue CofO | OGANES TARAKHCHYAN |