648 N CHAUTAUQUA BLVD 90272

Certificate Information: 648 N CHAUTAUQUA BLVD 90272

Application / Permit
22016-20000-12324
Plan Check / Job No.
B22VN06159
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ACCESSORY LIVING QUARTERS TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 11/10/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 NILOOFAR MEHRAIN
Corrections Issued 5/17/2022 NILOOFAR MEHRAIN
Quality Review Completed 5/24/2022 STEVEN KIM
Building Plans Picked Up 5/24/2022 APPLICANT
Plan Check Approved 10/21/2022 NILOOFAR MEHRAIN
Issued 11/10/2022 APPLICANT
CofO in Progress 5/17/2023 DANIEL ORRANTE
CofO in Progress 5/18/2023 OGANES TARAKHCHYAN
Permit Finaled 5/30/2023 DANIEL ORRANTE
CofO Issued 5/30/2023 DANIEL ORRANTE
Permit Finaled 5/30/2023 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 5/27/2022 DANIEL CORONADO
Miscellaneous Cleared 5/27/2022 DANIEL CORONADO
ZA Case Cleared 5/27/2022 DANIEL CORONADO
ZA Case Cleared 5/27/2022 DANIEL CORONADO
ZA Case Cleared 5/27/2022 DANIEL CORONADO
Address approval Cleared 5/31/2022 JENSON LEE
Sewer availability Cleared 5/31/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 6/21/2022 JENSON LEE
Hydrant and Access approval Cleared 10/11/2022 LAVEON RIDER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/9/2023 Corrections Issued OGANES TARAKHCHYAN
Pre-Inspection 3/10/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Gas Test 4/6/2023 Approved OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 4/6/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/13/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/27/2023 Approved OGANES TARAKHCHYAN
Final 4/27/2023 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/27/2023 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 4/27/2023 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 4/27/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 5/3/2023 Approved OGANES TARAKHCHYAN
Final 5/3/2023 Partial Approval OGANES TARAKHCHYAN
HVAC-Final 5/3/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Final 5/3/2023 Approved OGANES TARAKHCHYAN
Final 5/17/2023 OK to Issue CofO OGANES TARAKHCHYAN