14838 W AZTEC ST 91342
Certificate Information: 14838 W AZTEC ST 91342
- Application / Permit
- 22016-20000-12316
- Plan Check / Job No.
- B22VN06155
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL OF EXISTING SINGLE FAMILY DWELLING TO INCLUDE REMOVAL OF LOAD BEARING WALL- ALL WORK PER ENGINEER
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/29/2022
Permit Application Status History
| Submitted | 4/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 4/23/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 5/16/2022 | DANIEL ABRAMYAN |
| Issued | 5/17/2022 | APPLICANT |
| Building Plans Picked Up | 5/18/2022 | APPLICANT |
| Permit Finaled | 7/28/2022 | JENNIFER RABUCHIN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Aria Construction Inc; Lic. No.: 1082478-B | 18960 VENTURA BLVD #201 TARZANA, CA 91356 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/2/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/16/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/16/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/16/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/16/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/16/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 6/22/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/22/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/22/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/30/2022 | Approved | JOHN KIDWELL |
| Final | 7/25/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 7/25/2022 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 7/28/2022 | Approved | JENNIFER RABUCHIN |
| Final | 7/28/2022 | Permit Finaled | JENNIFER RABUCHIN |
| HVAC-Final | 7/28/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/28/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/28/2022 | Approved | JENNIFER RABUCHIN |