18153 W RAYEN ST 91325
Certificate Information: 18153 W RAYEN ST 91325
- Application / Permit
- 22016-20000-12272
- Plan Check / Job No.
- B22VN06134
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED 22' X 37' RECREATIONAL ROOM INTO AN ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A) - ALL WORK PER WFPP
- Permit Issued
- Issued on 7/12/2022
- Issuing Office
- Current Status
- CofO Issued on 3/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 4/30/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 6/23/2022 | DANIEL ABRAMYAN |
| Building Plans Picked Up | 6/27/2022 | APPLICANT |
| Issued | 7/12/2022 | APPLICANT |
| CofO in Progress | 12/23/2022 | DAVID SCANTLIN |
| Permit Finaled | 3/10/2023 | DANIEL ORRANTE |
| CofO Issued | 3/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 5/10/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2022 | CHRIS CHAHBAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/22/2022 | Corrections Issued | DAVID SANDOVAL |
| Sewer | 9/28/2022 | Approved | KRISTEN CAUSEY |
| Underground Mechanical | 9/28/2022 | Partial Approval | KRISTEN CAUSEY |
| Deputy Drilled-In Anchors | 9/30/2022 | Conditional Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 10/11/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 10/11/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 10/11/2022 | Approved | DAVID SCANTLIN |
| Shower Pan | 10/11/2022 | Approved | DAVID SCANTLIN |
| Insulation | 10/18/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/18/2022 | Partial Approval | KRISTEN CAUSEY |
| Drywall Nailing | 10/25/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 10/25/2022 | Approved | MORRIS JACKSON |
| Green Building Rough | 11/1/2022 | No Access for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/4/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 11/4/2022 | Approved | DAVID SCANTLIN |
| Green Building Final | 12/6/2022 | Corrections Issued | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 12/6/2022 | Approved | JOHN KIDWELL |
| Green Building Final | 12/13/2022 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Not Ready | JOHN KIDWELL |
| Special/Order Compliance | 12/13/2022 | Partial Inspection | MORRIS JACKSON |
| Final | 12/21/2022 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 12/21/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 3/3/2023 | Approved | WILLIAM MICHALAK |