228 E REDLANDS ST 90293
Certificate Information: 228 E REDLANDS ST 90293
- Application / Permit
- 22016-20000-12059
- Plan Check / Job No.
- B22VN05990
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ROOF ABOVE LOWER FLOOR TO ROOF DECK, ADD A NEW SPIRAL STAIRS TO ACCESS TO (N) ROOF DECK, AND INT AND EXT. REMODEL TO (E) SINGLE FAMILY DWELLING; NEW STEEL SPIRAL STAIRS PER LA CITY STANDARD PLAN #111
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 6/7/2024
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | SEAN SHAHMIRI |
| Corrections Issued | 5/24/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 5/25/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/1/2022 | APPLICANT |
| Applicant returned to address corrections | 8/31/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 9/21/2022 | SEAN SHAHMIRI |
| Issued | 2/21/2023 | APPLICANT |
| Permit Finaled | 6/6/2024 | BOBBY KEY |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/18/2022 | SEAN SHAHMIRI |
| Coastal Zone | Cleared | 9/6/2022 | SHASHA YU |
| Coastal Zone | Cleared | 9/6/2022 | SHASHA YU |
| Coastal Zone | Cleared | 9/6/2022 | SHASHA YU |
Contact Information
| Contractor | Caltron Construction Inc; Lic. No.: 725052-B | 3045 EAST 12TH STREET LOS ANGELES, CA 90023 |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 329 N HUBBARD AVE SAN FERNANDO, CA 91340 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/14/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/14/2023 | Approved | JESUS RODRIGUEZ |
| Pre-Inspection | 3/14/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 6/28/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 6/28/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 7/27/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 8/1/2023 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 8/23/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 9/6/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 9/6/2023 | Approved | BOBBY KEY |
| Structural Steel Frame | 9/6/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 10/12/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/31/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 11/20/2023 | Partial Approval | BOBBY KEY |
| Insulation | 11/20/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 12/4/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/4/2023 | Partial Approval | BOBBY KEY |
| Insulation | 12/11/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 12/14/2023 | Not Ready for Inspection | BOBBY KEY |
| Drywall Nailing | 12/15/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/26/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 2/26/2024 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 4/10/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/2/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 5/22/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 5/22/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 5/28/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 5/28/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 5/29/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/29/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 6/3/2024 | Corrections Issued | BOBBY KEY |
| Final | 6/3/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 6/3/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 6/3/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/3/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 6/3/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/6/2024 | Approved | BOBBY KEY |
| Final | 6/6/2024 | Permit Finaled | BOBBY KEY |
| HVAC-Final | 6/6/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Approved | BOBBY KEY |