22954 W RUNNYMEDE ST 91307
Certificate Information: 22954 W RUNNYMEDE ST 91307
- Application / Permit
- 22016-20000-12058
- Plan Check / Job No.
- B22VN05987
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 20'x20'DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/19/2022
- Issuing Office
- Current Status
- CofO Issued on 9/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2022 | JESSE ARELLANO |
| Corrections Issued | 4/28/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 5/19/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 6/15/2022 | APPLICANT |
| Issued | 7/19/2022 | APPLICANT |
| CofO in Progress | 3/13/2023 | KRISTEN BEVERIDGE |
| Permit Finaled | 9/29/2023 | JOHN JANSON |
| CofO Issued | 9/29/2023 | JOHN JANSON |
| Permit Finaled | 9/29/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/6/2022 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 6/14/2022 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/10/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/16/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 11/16/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Special/Order Compliance | 11/16/2022 | Partial Inspection | JESUS PINEDA |
| PLUMBING-Rough | 12/8/2022 | Corrections Issued | KRISTEN CAUSEY |
| Sewer | 12/8/2022 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 12/19/2022 | Partial Inspection | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 12/19/2022 | Partial Inspection | KRISTEN CAUSEY |
| Insulation | 12/19/2022 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/20/2022 | Corrections Issued | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 12/20/2022 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 12/20/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/23/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Rough | 12/23/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| Drywall Nailing | 12/30/2022 | Approved | KRISTEN CAUSEY |
| Insulation | 12/30/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 12/30/2022 | Approved | KRISTEN CAUSEY |
| Shower Pan | 12/30/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/24/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Final | 2/24/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Final | 2/24/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Rough | 2/24/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Not Ready | KRISTEN CAUSEY |
| Smoke Detectors | 2/24/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Pre-Inspection | 3/3/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 3/10/2023 | Approved | KRISTEN CAUSEY |
| Final | 3/10/2023 | OK to Issue CofO | KRISTEN CAUSEY |
| Green Building Final | 3/10/2023 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 3/10/2023 | Approved | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Approved | KRISTEN CAUSEY |
| Smoke Detectors | 3/10/2023 | Approved | KRISTEN CAUSEY |