8645 N CASABA AVE 91306

Certificate Information: 8645 N CASABA AVE 91306

Application / Permit
22016-20000-11773
Plan Check / Job No.
B22VN05823
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED 2-CAR GARAGE TO ADU PER CA GC 65852.2(e)(1)(A). ALL CONSTRUCTION PER WFPP
Permit Issued
Issued on 7/8/2022
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 VIVIAN LAO
Corrections Issued 4/22/2022 VIVIAN LAO
Plan Check Approved 6/7/2022 VIVIAN LAO
Issued 7/8/2022 APPLICANT
CofO in Progress 1/13/2023 CHRIS CHRISTENSEN
CofO Issued 1/19/2023 JOHN JANSON
Permit Finaled 1/19/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/26/2022 ROMAN GUTIERREZ
Sewer availability Cleared 4/26/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/6/2022 ROMAN GUTIERREZ
Construction within easement Cleared 6/1/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/1/2022 Conditional Approval CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 8/8/2022 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 8/10/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 8/30/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 8/30/2022 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/2/2022 Corrections Issued CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 9/13/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/13/2022 Partial Approval CHRIS CHRISTENSEN
Wood Frame 9/13/2022 Approved CHRIS CHRISTENSEN
Insulation 9/26/2022 Approved JESUS PINEDA
Drywall Nailing 10/11/2022 Approved JUSTIN HAWLEY
Pre-Inspection 10/11/2022 Approved JUSTIN HAWLEY
Final 12/29/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 12/29/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 12/29/2022 Approved CHRIS CHRISTENSEN
Pre-Inspection 1/3/2023 Not Ready for Inspection KRISTEN CAUSEY
Final 1/5/2023 Conditional Approval CHRIS CHRISTENSEN
Final 1/12/2023 OK to Issue CofO CHRIS CHRISTENSEN