5555 N CEDROS AVE 91411
Certificate Information: 5555 N CEDROS AVE 91411
- Application / Permit
- 22016-20000-11692
- Plan Check / Job No.
- B22VN05771
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF THE EXISTING 20'-0" X 20'-0" GARAGE INTO AN ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) - ALL WORK PER ENGINEER
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Current Status
- CofO Issued on 10/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 4/26/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 5/28/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 7/7/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 7/13/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 7/13/2022 | DANIEL ABRAMYAN |
| Issued | 7/14/2022 | APPLICANT |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| CofO in Progress | 10/3/2022 | JACK KARGODORIAN |
| Permit Finaled | 10/4/2022 | MICHAEL SMITH |
| CofO Issued | 10/4/2022 | MICHAEL SMITH |
| Permit Finaled | 10/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 5/24/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 5/24/2022 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 5/24/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 5/24/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 5/24/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 5/24/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/19/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 7/19/2022 | Partial Approval | MISAEL ESPARZA |
| Sewer | 7/19/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/25/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 7/25/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Sewer | 7/25/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 7/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 7/27/2022 | Partial Approval | JACK KARGODORIAN |
| Sewer | 7/27/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/1/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/1/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 8/1/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 8/1/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Sewer | 8/1/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/3/2022 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/3/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/3/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/8/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/8/2022 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 8/8/2022 | Partial Approval | JACK KARGODORIAN |
| Insulation | 8/8/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 8/9/2022 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/17/2022 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/17/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Approved | CALEB MEISTER |
| Insulation | 8/19/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 8/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| Shower Pan | 8/19/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 8/24/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/24/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/23/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 9/23/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 9/23/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 9/23/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 9/23/2022 | Approved | JACK KARGODORIAN |
| HVAC-Final | 9/23/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 9/23/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 9/23/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 10/3/2022 | Approved | JACK KARGODORIAN |
| Final | 10/3/2022 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 10/3/2022 | Approved | JACK KARGODORIAN |
| HVAC-Final | 10/3/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 10/3/2022 | Approved | JACK KARGODORIAN |