6518 W COLGATE AVE 90048
Certificate Information: 6518 W COLGATE AVE 90048
- Application / Permit
- 22016-20000-11642
- Plan Check / Job No.
- B22VN05734
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/2/2022
- Issuing Office
- Current Status
- CofO Issued on 4/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 4/23/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Applicant returned to address corrections | 10/26/2022 | MINA HABILI |
| Plan Check Approved | 11/2/2022 | STANLEY RAAP |
| Issued | 11/2/2022 | APPLICANT |
| CofO in Progress | 3/17/2023 | JEREMY TODD |
| Permit Finaled | 4/7/2023 | DANIEL ORRANTE |
| CofO Issued | 4/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2022 | CINDY QI |
| Sewer availability | Cleared | 4/28/2022 | CINDY QI |
| Construction near power lines | Cleared | 5/24/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 5/24/2022 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2022 | AMY SHUM |
Contact Information
| Contractor | Caliwood Development Inc; Lic. No.: 1016617-B | 205 S HAMEL DR BEVERLY HILLS, CA 90211 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/13/2022 | Not Ready for Inspection | JEREMY TODD |
| Special/Order Compliance | 12/13/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 12/13/2022 | Corrections Issued | JEREMY TODD |
| Footing/Foundation/Slab | 12/15/2022 | Corrections Issued | JEREMY TODD |
| PLUMBING-Rough | 12/15/2022 | Partial Approval | JEREMY TODD |
| Special/Order Compliance | 12/15/2022 | Partial Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/19/2022 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 1/17/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 1/17/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 1/17/2023 | Approved | JEREMY TODD |
| Deputy Wood Construction | 1/18/2023 | Conditional Approval | JEREMY TODD |
| Deputy Wood Construction | 1/20/2023 | Conditional Approval | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 1/25/2023 | Approved | JEREMY TODD |
| Shower Pan | 1/25/2023 | Approved | JEREMY TODD |
| Insulation | 2/2/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 2/7/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 3/8/2023 | Approved | JEREMY TODD |
| HVAC-Final | 3/8/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 3/8/2023 | Approved | JEREMY TODD |
| Service/Power Release | 3/8/2023 | Not Ready for Inspection | JEREMY TODD |
| BUILDING-Rough-Frame | 3/14/2023 | Approved | JEREMY TODD |
| Final | 3/14/2023 | Corrections Issued | JEREMY TODD |
| Green Building Final | 3/14/2023 | Approved | JEREMY TODD |
| Green Building Rough | 3/14/2023 | Approved | JEREMY TODD |
| METHANE-Final | 3/14/2023 | Approved | JEREMY TODD |
| METHANE-Rough | 3/14/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Approved | JEREMY TODD |
| Smoke Detectors | 3/14/2023 | Approved | JEREMY TODD |
| Final | 3/16/2023 | OK to Issue CofO | JEREMY TODD |
| Service/Power Release | 3/16/2023 | Approved | JEREMY TODD |