2208 S OVERLAND AVE 90064

Certificate Information: 2208 S OVERLAND AVE 90064

Application / Permit
22016-20000-11344
Plan Check / Job No.
B22VN05605
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20' X 18' EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ALL WORK PER WFPP.
Permit Issued
Issued on 8/2/2022
Issuing Office
Current Status
CofO Issued on 12/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2022 APPLICANT
Assigned to Plan Check Engineer 4/15/2022 DANIEL ABRAMYAN
Corrections Issued 4/16/2022 DANIEL ABRAMYAN
Building Plans Picked Up 4/21/2022 APPLICANT
Plan Check Approved 8/2/2022 SERGIO MUNIZ
Plan Check Approved 8/2/2022 SERGIO MUNIZ
Issued 8/2/2022 APPLICANT
CofO in Progress 12/1/2022 CARLOS MATAMOROS
Permit Finaled 12/27/2022 DANIEL ORRANTE
CofO Issued 12/27/2022 DANIEL ORRANTE
Permit Finaled 12/27/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/12/2022 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 5/12/2022 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 5/13/2022 VLADIMIR ARUTYUNYAN
Construction near power lines Cleared 7/7/2022 TINA MIRANDA
Construction within easement Cleared 7/7/2022 TINA MIRANDA
Grading Pre-Inspection Cleared 7/14/2022 ROBERT HUGHES
Specific Plan Cleared 7/28/2022 FREDDY GARCIA

Contact Information

Contractor C & L Construction Inc; Lic. No.: 992723-B 17000 VENTURA BLVD STE 203      ENCINO, CA 91316

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/2/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 9/2/2022 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 9/12/2022 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/12/2022 Partial Approval MICHAEL PELHAM
PLUMBING-Rough 9/12/2022 Not Ready for Inspection MICHAEL PELHAM
Footing/Foundation/Slab 9/16/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 9/16/2022 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 9/30/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 9/30/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 9/30/2022 Not Ready for Inspection STEPHANIE SWANSON
Wood Frame 9/30/2022 Not Ready for Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 10/5/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 10/5/2022 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 10/5/2022 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 10/5/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 10/12/2022 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 10/12/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 10/12/2022 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 10/12/2022 Approved STEPHANIE SWANSON
Insulation 10/14/2022 Corrections Issued STEPHANIE SWANSON
Drywall Nailing 10/21/2022 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 10/25/2022 Approved STEPHANIE SWANSON
Green Building Rough 10/25/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 10/25/2022 Approved STEPHANIE SWANSON
METHANE-Rough 10/25/2022 Approved STEPHANIE SWANSON
Shower Pan 10/25/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 11/14/2022 Corrections Issued STEPHANIE SWANSON
Final 11/14/2022 Corrections Issued STEPHANIE SWANSON
Green Building Final 11/14/2022 Approved STEPHANIE SWANSON
HVAC-Final 11/14/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 11/14/2022 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 11/14/2022 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 11/14/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 11/30/2022 Approved CARLOS MATAMOROS
Final 11/30/2022 OK to Issue CofO CARLOS MATAMOROS
HVAC-Final 11/30/2022 Approved CARLOS MATAMOROS
PLUMBING-Final 11/30/2022 Approved CARLOS MATAMOROS