1731 S CARMELINA AVE 90025

Certificate Information: 1731 S CARMELINA AVE 90025

Application / Permit
22016-20000-11185
Plan Check / Job No.
B22VN05487
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX. DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER ENGINEER. "COMPLY WITH DEPARTMENT ORDER effective date 02/28/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
Permit Issued
Issued on 9/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2022 APPLICANT
Assigned to Plan Check Engineer 4/15/2022 DANIEL ABRAMYAN
Corrections Issued 4/16/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 6/23/2022 DANIEL ABRAMYAN
Building Plans Picked Up 6/24/2022 APPLICANT
Plan Check Approved 9/6/2022 ROSENDO MEDINA
Issued 9/15/2022 APPLICANT
CofO in Progress 3/30/2023 RYAN BARNES
CofO Issued 4/27/2023 BRUCE TODD
Permit Finaled 4/27/2023 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 4/23/2022 JOSE HERNANDEZ
Sewer availability Cleared 4/23/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 4/25/2022 JOSE HERNANDEZ
Specific Plan Cleared 5/25/2022 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/25/2022 Not Ready for Inspection RYAN BARNES
Pre-Inspection 11/10/2022 Conditional Approval RYAN BARNES
Footing/Foundation/Slab 11/28/2022 Conditional Approval RYAN BARNES
Wood Frame 12/15/2022 Partial Approval RYAN BARNES
Insulation 12/21/2022 Approved RYAN BARNES
Interior/Exterior Lathing 12/21/2022 Approved RYAN BARNES
PLUMBING-Rough 12/21/2022 Approved RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Approved RYAN BARNES
Drywall Nailing 1/4/2023 No Access for Inspection RYAN BARNES
ELECTRICAL-Rough 1/6/2023 Not Ready for Inspection MARIAN PODPORA
Grounding or Bonding 1/6/2023 Not Ready for Inspection MARIAN PODPORA
Drywall Nailing 1/13/2023 Approved JOHN MATTILLO
ELECTRICAL-Final 1/13/2023 Not Ready for Inspection JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Approved RYAN BARNES
ELECTRICAL-Final 2/1/2023 Partial Approval RYAN BARNES
Service/Power Release 3/2/2023 Approved RYAN BARNES
Service/Power Release 3/7/2023 Approved RYAN BARNES
BUILDING-Rough-Frame 3/22/2023 Approved ANDREW BEELI
Final 3/22/2023 Corrections Issued ANDREW BEELI
Green Building Final 3/22/2023 Not Ready for Inspection ANDREW BEELI
Green Building Rough 3/22/2023 Approved ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 3/22/2023 SGSOV Approved ANDREW BEELI
Smoke Detectors 3/22/2023 Approved ANDREW BEELI
Final 3/30/2023 Conditional Approval RYAN BARNES
Green Building Final 3/30/2023 Approved RYAN BARNES