6828 N WOODMAN AVE 91405
Certificate Information: 6828 N WOODMAN AVE 91405
- Application / Permit
- 22016-20000-11165
- Plan Check / Job No.
- B22VN05474
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 40' GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g).
- Permit Issued
- Issued on 6/13/2022
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2022 | OMAR GARNICA |
| Corrections Issued | 4/16/2022 | OMAR GARNICA |
| Plan Check Approved | 6/13/2022 | OMAR GARNICA |
| Issued | 6/13/2022 | APPLICANT |
| Building Plans Picked Up | 6/14/2022 | APPLICANT |
| CofO in Progress | 4/11/2023 | JUAN VALENZUELA |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/19/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Imperial Builders Inc; Lic. No.: 1035713-B | 13704 VANOWEN STREET VAN NUYS, CA 91405 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/23/2022 | Partial Inspection | CAMERON CHABAN |
| Deputy Drilled-In Anchors | 9/2/2022 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 9/2/2022 | Conditional Approval | CAMERON CHABAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Conditional Approval | CAMERON CHABAN |
| Interior/Exterior Lathing | 10/6/2022 | Conditional Approval | CAMERON CHABAN |
| BUILDING-Rough-Frame | 10/7/2022 | Approved | RAFAEL CORTES |
| ELECTRICAL-Rough | 10/7/2022 | Approved | RAFAEL CORTES |
| HVAC-Rough | 10/7/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Rough | 10/7/2022 | Approved | RAFAEL CORTES |
| Insulation | 10/12/2022 | Approved | MICHAEL SMITH |
| Drywall Nailing | 10/19/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/19/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/5/2022 | Approved | KIRK SANDERS |
| Final | 12/5/2022 | OK to Issue CofO | KIRK SANDERS |
| Green Building Final | 12/5/2022 | Approved | KIRK SANDERS |
| Green Building Rough | 12/5/2022 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/5/2022 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 12/5/2022 | Approved | KIRK SANDERS |